the folsom rams project is a project that is part of the transbay redevelopment program. the purpose of the project is to realign the off ramp at folsom and fremont. as you see in this -- as you see in this drawing, the ramp on the right side crosses the whole block 8, making it hard to develop that block. and, so, the purpose of this project is basically to realign the ramp, having the ramp that now goes to folsom run parallel to the one on fremont. [speaker not understood] as shown in this drawing. in september 2007, the san francisco redevelopment agency entered into an agreement with the authority for managing this project. basically the job of the authority was to conduct a solicitation to hire a consultant and to manage the process with the consultant ands caltrans. in february 2008, the authority ~ entered into a contract for $200,000 with mark thomas and company for doing the planning, environmental, and engineering services for the project. however, before the project was completed, the state decided the redevelopment agency in 2011, therefore the project was put