BY ORDER OF THE COMMANDER 



SMC Standard SMC-S-012 
13 June 2008 


Supersedes: 
New issue 


Air Force Space Command 

SPACE AND MISSILE SYSTEMS CENTER 

STANDARD 

SOFTWARE 
DEVELOPMENT 
FOR SPACE SYSTEMS 


APPROVED FOR PUBLIC RELEASE; DISTRIBUTION IS UNLIMITED 




Report Documentation Page 

Form Approved 

OMB No. 0704-0188 

Public reporting burden for the collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, searching existing data sources, gathering and 
maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, 
including suggestions for reducing this burden, to Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington 

VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to a penalty for failing to comply with a collection of information if it 
does not display a currently valid OMB control number. 

1. REPORT DATE 2. REPORT TYPE 

13 JUN 2008 N/A 

3. DATES COVERED 

4. TITLE AND SUBTITLE 

SMC-S-012 (2008) Software Development for Space Systems 

5a. CONTRACT NUMBER 

5b. GRANT NUMBER 

5c. PROGRAM ELEMENT NUMBER 

6. AUTHOR(S) 

5d. PROIECT NUMBER 

5e. TASK NUMBER 

5f. WORK UNIT NUMBER 

7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) 

USAF Space and Missile Systems Center 

8. PERFORMING ORGANIZATION 

REPORT NUMBER 

9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 

10. SPONSOR/MONITOR'S ACRONYM(S) 

11. SPONSOR/MONITOR'S REPORT 
NUMBER(S) 

12. DISTRIBUTION/AVAILABILITY STATEMENT 

Approved for public release, distribution unlimited 

13. SUPPLEMENTARY NOTES 

14. ABSTRACT 

15. SUBIECT TERMS 

16. SECURITY CLASSIFICATION OF: 17. LIMITATION OF 

18. NUMBER 19a. NAME OF 

a. REPORT b. ABSTRACT c. THIS PAGE |J|J 

unclassified unclassified unclassified 

83 


Standard Form 298 (Rev. 8-98) 

Prescribed by ANSI Std Z39-18 






FOREWORD 


1. This standard defines the Government’s requirements and expectations for contractor 
performance in defense system acquisitions and technology developments. 

2. This new-issue SMC standard comprises the text of The Aerospace Corporation report 

number TOR-2004(3909)-3537, Rev B. P 

3. Beneficial comments (recommendations, changes, additions, deletions, etc.) and any 
pertinent data that may be of use in improving this standard should be forwarded to the following 
addressee using the Standardization Document Improvement Proposal appearing at the end of this 
document or by letter: 


Division Chief, SMC/EAE 
SPACE AND MISSILE SYSTEMS CENTER 
Air Force Space Command 
483 N. Aviation Blvd. 

El Segundo, CA 90245 


4. This standard has been approved for use on all Space and Missile Systems 
Center/Air Force Program Executive Office - Space development, acquisition, and 
sustainment contracts. 



James Horejsi, Col, USAF 
SMC Chief Engineer 




Contents 


1. Scope.1 

1.1 Purpose.1 

1.2 Application.1 

1.3 Order of precedence.3 

2. Referenced Documents.5 

3. Definitions.7 

3.1 Terms.7 

4. General Requirements.13 

4.1 Software development process.13 

4.2 General requirements for software development.13 

5. Detailed Requirements.17 

5.1 Project planning and oversight.17 

5.2 Establishing a software development environment.18 

5.3 System requirements analysis.19 

5.4 System design.20 

5.5 Software requirements analysis.21 

5.6 Software design.21 

5.7 Software implementation and unit testing.22 

5.8 Unit integration and testing.23 

5.9 Software item qualification testing.24 

5.10 Software/hardware item integration and testing.26 

5.10.1 Preparing for software/hardware item integration and testing.26 

5.10.2 Performing software/hardware item integration and testing.27 

5.10.3 Revision and retesting.27 

5.10.4 Analyzing and recording software/hardware item integration and test results.27 

5.11 System qualification testing.27 

5.11.1 Independence in system qualification testing.28 

5.11.2 Testing on the target computer system.28 

5.11.3 Preparing for system qualification testing.28 

5.11.4 Dry run of system qualification testing.28 

5.11.5 Performing system qualification testing.28 

5.11.6 Revision and retesting.28 

5.11.7 Analyzing and recording system qualification test results.28 

5.12 Preparing for software transition to operations.28 

5.12.1 Preparing the executable software.29 

5.12.2 Preparing version descriptions for user sites.29 

5.12.3 Preparing user manuals.29 

5.12.3.1 Software user manuals.29 

5.12.3.2 Computer operation manuals.29 

5.12.4 Installation at user sites.29 

5.13 Preparing for software transition to maintenance.30 

5.13.1 Preparing the executable software.30 

5.13.2 Preparing source files.30 

5.13.3 Preparing version descriptions for the maintenance site.30 

5.13.4 Preparing the “as built” software item design and related information.30 
















































5.13.5 Updating the system/subsystem design description.31 

5.13.6 Updating the software requirements.31 

5.13.7 Updating the system requirements.31 

5.13.8 Preparing maintenance manuals.31 

5.13.8.1 Computer programming manuals.31 

5.13.8.2 Firmware support manuals.32 

5.13.9 Transition to the designated maintenance site.32 

5.14 Software configuration management.32 

5.14.1 Configuration identification.32 

5.14.2 Configuration control.32 

5.14.3 Configuration status accounting.33 

5.14.4 Configuration audits.33 

5.14.5 Packaging, storage, handling, and delivery.33 

5.15 Software peer reviews and product evaluations.33 

5.15.1 Software peer reviews.33 

5.15.1.1 Prepare for software peer reviews.33 

5.15.1.2 Conduct peer reviews.34 

5.15.1.3 Analyze peer review data.34 

5.15.2 Software product evaluations.34 

5.15.2.1 In-process and final software product evaluations.34 

5.15.2.2 Software product evaluation records.34 

5.15.2.3 Independence in software product evaluation.35 

5.16 Software quality assurance.35 

5.16.1 Software quality assurance evaluations.35 

5.16.2 Software quality assurance records.35 

5.16.3 Independence in software quality assurance.35 

5.16.4 Software quality assurance noncompliance issues.35 

5.17 Corrective action.36 

5.17.1 Problem/change reports.36 

5.17.2 Corrective action system.36 

5.18 Joint technical and management reviews.36 

5.18.1 Joint technical reviews.37 

5.18.2 Joint management reviews.37 

5.19 Risk management.37 

5.20 Software management indicators.37 

5.21 Security and privacy.38 

5.22 Subcontractor management.38 

5.23 Interface with software IV&V agents.38 

5.24 Coordination with associate developers.38 

5.25 Improvement of project processes.38 

6. Notes.39 

6.1 Intended use.39 

6.2 Data Item Descriptions (DIDs).39 

6.3 Relationship between standard and CDRL.40 

6.4 Delivery of tool contents.40 

6.5 Tailoring guidance.40 

6.6 Related standardization documents.40 

6.7 Subject term (key word) listing.41 

Appendix A. List of acronyms.A-1 

A.l Scope.A-l 

A.2 Acronyms.A-l 






















































Appendix B. Interpreting this standard for incorporation of COTS and reusable software products 


.B-l 

B.l Scope.B-l 

B.2 Evaluating reusable software products.B-1 

B. 3 Interpreting this standard’s activities for reusable software products.B-3 

Appendix C. Category and severity classifications for problem reporting.C-l 

C. l Scope.C-l 

C.2 Classification by category.C-l 

C. 3 Classification by severity.C-3 

Appendix D. Software product evaluations.D-l 

D. l Scope.D-l 

D.2 Required evaluations.D-l 

D. 3 Criteria definitions.D-l 

Appendix E. Candidate joint management reviews.E-1 

E. l Scope.E-l 

E.2 Assumptions.E-l 

E.3 Candidate reviews.E-l 

E.3.1 Software plan reviews.E-l 

E.3.2 Operational concept reviews.E-l 

E.3.3 System/Subsystem requirements reviews.E-l 

E.3.4 System/Subsystem design reviews.E-l 

E.3.5 Software requirements reviews.E-2 

E.3.6 Software design reviews.E-2 

E.3.7 Test readiness reviews.E-2 

E.3.8 Test results reviews.E-2 

E.3.9 Software usability reviews.E-2 

E.3.10 Software maintenance reviews.E-2 

E. 3.11 Critical requirements reviews.E-2 

Appendix F. Candidate management indicators.F-1 

F. l Scope.F-l 

F. 2 Candidate indicators.F-l 

Appendix G. Guidance on contracting for delivery of software products.G-l 

G. l Scope.G-l 

G.2 Contracting for deliverables.G-l 

G.3 Scheduling deliverables.G-l 

G.4 Format of deliverables.G-l 

G.5 Tailoring the content requirements for deliverables.G-2 

Appendix H. Software Development Plan Template.H-l 








































Figures 


Figure C.2-1 Example categories of software products.C-l 

Figure C.2-2 Example categories of software activities.C-2 

Figure C.3-1 Example scheme for classifying problems by severity.C-3 

Figure D.3-1 Software products and associated evaluation criteria.D-4 







1. Scope 


1.1 Purpose 

The purpose of this standard is to establish uniform requirements for software development activities. 

1.2 Application 2 

This standard applies to the development of systems that contain software (such as hardware-software 
systems), software-only systems, and stand-alone software products. The application of this standard 
is intended as follows. 

1.2.1 Organizations and agreements 

This standard can be applied to contractors, subcontractors, or government in-house agencies 
performing software development. Within this standard, the term “acquirer” is used for the 
organization requiring the technical effort; the term “developer” is used for the organization 
performing the technical effort; the term “contract” is used for the agreement between these parties; 
the term “Statement of Work” (SOW) is used for the list of tasks to be performed by the developer; 
the term “Contract Data Requirements List” (CDRL) is used for the list of deliverable software 
products; and the term “subcontractor” is used for any organization tasked by the developer to 
perform part of the required effort. “Software development” is used as an inclusive term 
encompassing new development, modification, reuse, reengineering, maintenance, and all other 
activities resulting in software products. 

1.2.2 Contract-specific application 

This standard is invoked by citing it on a contract. It applies to each software product and to each 
type of software covered by the contract, regardless of storage medium, to the extent specified in the 
contract. The acquirer is expected to specify the types of software to which the standard applies and 
to tailor the standard appropriately for each type of software. While this standard is written in terms 
of software items, it may be applied to software not designated as a software item, with the term 
“software item” interpreted appropriately. Software installed in firmware is subject to all of the 
aforementioned provisions. This standard does not apply to the hardware element of firmware. 

Unless specified otherwise in the contract, for SMC and NRO programs, this standard shall apply to 
the prime contractor and all significant software team members. This standard shall apply to the 
following categories of software: onboard software (e.g., spacecraft, communications, payload); 
ground operations software (e.g., mission planning; mission processing; mission support; telemetry, 
tracking, and commanding; infrastructure and services); and other software used in satisfying, 
verifying, or validating requirements or used in performing or supporting operations or sustainment 
(e.g., training, simulation, analysis, database support, automatic test equipment, and maintenance). A 
software team member is any internal or external organization that develops, tests, or supports 
software-related work being performed for this contract and has an agreement (formal or informal) 
with the prime contractor or any other software team member. These organizations include, but are 
not limited to, intra-corporation software organizations, in-house service providers, developers, 
fabrication/manufacturing organizations, laboratories, and subcontractors. Examples of an agreement 
include a contract, work authorization, memorandum of agreement, or oral agreement. A significant 
software team member is a software team member with significant software development 


- This is based on information from Section 1 of J-STD-016-1995 [6], 


1 



responsibility. Significant software development responsibility includes responsibility for any 
category of software described above. 

1.2.3 Tailoring 

This standard can be tailored for each type of software to which it is applied. While tailoring is the 
responsibility of the acquirer, prospective and selected developers may provide suggested tailoring. 
General tailoring guidance can be found in Section 6.5. 

1.2.4 Compliance 

Compliance with this standard as tailored for a project and recorded in the contract is defined as: 

a) Performing the activities that resulted from tailoring this standard for a specific project, 

b) Recording applicable information resulting from the performance of the activities. 

An activity is complete when all actions constituting the activity, as specified in the contract or 
agreement, have been accomplished and all applicable information has been recorded. 

1.2.5 Interpretation of selected terms 

The following terms have a special interpretation as used in this standard. 

1.2.5.1 Interpretation of “system” 

The following inteipretations apply: 

a) The term “system,” as used in this standard, may mean: 

1) A hardware-software system (for example, a radar system) for which this standard covers 
only the software portion, or 

2) A software system (for example, a payroll system) for which this standard governs 
overall development. 

For most SMC and NRO programs, software is an integral part of the combined hardware- 
software space system. For these programs, this standard and its tailoring shall be interpreted 
in that context. 

b) If a system consists of subsystems (or segments), all requirements in this standard concerning 
systems apply to the subsystems (or segments) as well. If a contract is based on alternatives 
to systems and subsystems (or segments), such as complex items, the requirements in this 
standard concerning the system and its specification apply to these alternatives and their 
specifications. 

1.2.5.2 Interpretation of “participate” in system development 2 

The term “participate” in paragraphs regarding system-level activities is to be interpreted as follows: 

a) If the software covered by this standard is part of a hardware-software system for which this 
standard covers only the software portion, the term “participate” is to be interpreted as “take 
part in, as described in the SDP.” 

b) If the software (possibly with its computers) is considered to constitute a system, the term 
“participate” is to be interpreted as “be responsible for.” 

c) If the software in a hardware-software system is modified, but the hardware is not, the term 
“participate” may also be interpreted as “be responsible for.” 


2 



1.2.5.3 Interpretation of “develop,” “define,” etc. 

Throughout this standard, requirements to “develop,” “define,” “establish,” or “identify” information 
are to be interpreted to include new development, modification, reuse, reengineering, maintenance, or 
any other activity or combination of activities resulting in software products. 

1.2.5.4 Interpretation of “record” (the verb) 

Throughout this standard, requirements to “record” information are to be interpreted to mean “set 
down in a manner that can be retrieved and viewed.” The result may take many forms, including, but 
not limited to, hand-written notes, hard copy or electronic documents, and data recorded in computer- 
aided software engineering (CASE) and project management tools. 

1.2.5.5 Interpretation of “applicable” 

Within this standard, requirements to provide “applicable” information or to perform “applicable” 
activities are inteipreted as meaning to “provide the information or perform the activities that are 
required for the project in accordance with the methods, tools, and procedures explained in the 
Software Development Plan.” The term “applicable” suggests that not all development projects will 
require the information or the activity. The acquirer and the developer jointly agree upon whether 
providing information or performing activities are applicable. 

1.3 Order of precedence 

In the event of conflict between the requirements of this standard and other applicable standardization 
documents, the acquirer is responsible for resolving the conflicts. 


3 




2. Referenced Documents 


[1] Abelson, L. A., R. J. Adams, S. Eslinger. Metrics-based Software Acquisition Management. 
Aerospace Report No. TOR-2004(3909)3405. The Aerospace Corporation. May 2004. 

[2] Adams, R. J., S. Eslinger, P. Elantos, K. L. Owens, L. T. Stephenson, R. Weiskopf. 
Recommended Software Standards for Space Systems. Aerospace Report No. TOR- 
2004(3909)-3406. The Aerospace Corporation. May 2004. 

[3] Defense Acquisition University. GLOSSARY: Defense Acquisition Acronyms and Terms. 
September 2003. 

[4] Department of Defense. Software Development and Documentation. M1L-STD-498, December 
1994. 

[5] Department of Defense and U.S. Army. Practical Software and System Measurement. Version 
4.0c, March 2003. 

[6] Electronic Industries Association / Institute of Electrical and Electronic Engineers, Inc. 
EIA/IEEE Interim Standard J-STD-016-1995. Standard for Information Technology, Software 
Life Cycle Processes Software Development Acquirer-Supplier Agreement. September 1995. 

[7] Institute of Electrical and Electronics Engineers. IEEE Standard Classification for Software 
Anomalies. IEEE 1044-1993. January 1995 

[8] Institute of Electrical and Electronics Engineers. IEEE Standard Glossary of Software 
Engineering Terminology:. IEEE Std 610.12-1990. September 1990. 

[9] International Organization for Standards / International Electrotechnical Commission (ISO / 
IEC). Software Engineering - Software Measurement Process. International Organization for 
Standardization. ISO/IEC 15939. 2002. 

[10] McGarry, John, David Card, Cheryl Jones, Beth Layman, Elizabeth Clark, Joseph Dean and 
Fred Hall. Practical Software Measurement: Objective Information for Decision Makers. 
Addison Wesley, October 2001. 

[11] Software Engineering Institute. Capability Maturity Model Integration, Version 1.1, CMMIfor 
Systems Engineering, Software Engineering, Integrated Product and Process Development, and 
Supplier Sourcing (CMMI-SE/SW/IPPD/SS, VI.1), Continuous Representation. Carnegie 
Mellon University, SEI-2002-TR-011, March 2002. 

[12] Software Engineering Institute. Capability Maturity Model Integration, Version 1.1, CMMIfor 
Systems Engineering, Software Engineering, Integrated Product and Process Development, and 
Supplier Sourcing (CMMI-SE/SW/IPPD/SS, VI. 1), Staged Representation. Carnegie Mellon 
University, SEI-2002-TR-012, March 2002. 


5 



6 



3. Definitions 


3.1 Terms 

Acceptance . An action by an authorized representative of the acquirer by which the acquirer assumes 
ownership of software products as partial or complete performance of a contract. 

Acquirer . An organization that procures software products for itself or another organization. 

Approval . Written notification by an authorized representative of the acquirer that a developer’s 
plans, requirements, designs, or other aspects of the project appear to be sound and can be used as the 
basis for further work. Such approval does not shift responsibility from the developer to meet 
contractual requirements. 

Architecture . The organizational structure of a system or software item, identifying its components, 
their interfaces, and a concept of interaction among them. 

Associate developer . An organization that is neither prime contractor nor subcontractor to the 
developer, but who has a development role on the same or related system or project. 

Availability. This defines the probability that the system, prior to the start of a mission, will be 
mission capable when a mission is needed. Availability accounts for system faults and the time it 
takes to restore the system to a mission capable state following failure (maintainability). 

Behavioral design . The design of how an overall system or a software item will behave, from a user’s 
point of view, in meeting its requirements, ignoring the internal implementation of the system or the 
software item. This design contrasts with architectural design, which identifies the internal 
components of the system or the software item, and with the detailed design of those components. 

Build. 

(1) A version of software that meets a specified subset of the requirements that the completed 
software will meet. 

(2) The period of time during which such a version is developed. 

Note: The relationship of the terms “build” and “version” is up to the developer; for example, it may 
take several versions to reach a build, a build may be released in several parallel versions (such as to 
different sites), or the terms may be used as synonyms. 

Commercial off-the-shelf (COTS) software . See reusable software product. 

Computer database . See database. 

Computer hardware . Devices capable of accepting and storing computer data, executing a systematic 
sequence of operations on computer data, or producing control outputs. Such devices can perform 
substantial interpretation, computation, communication, control, or other logical functions. 


7 



Computer program . A combination of computer instructions and data definitions that enable 
computer hardware to perform computational or control functions. 

Computer software . See software. 

Computer software configuration item (CSCI) . See software item. 

Computer software unit (CSU). See software unit. 

Database . A collection of related data stored in one or more computerized files in a manner that can 
be accessed by users or computer programs via a database management system. 

Database management system . An integrated set of computer programs that provide the capabilities 
needed to establish, modify, make available, and maintain the integrity of a database. 

Data item description (DID) . The format and content preparation instructions for a data product 
generated by the specific and discrete task requirement as delineated in the contract. Examples 
include DIDs for the Software Development Plan (SDP), Software Design Description (SDD), 
Software Test Report (STR), and Software User Manual (SUM). See Section 6.2 for a list of DIDs 
applicable to this standard. 

Deliverable software product . A software product that is required by the contract to be delivered to 
the acquirer or other designated recipient. 

Dependability. This defines the probability that the system will be able to complete the mission even 
if there is a failure given the system was available at the start of the mission. Dependability accounts 
for system faults and the time it takes to restore the system to a mission capable state following 
failure (maintainability). 

Design . Those characteristics of a system or software item that are selected by the developer in 
response to the requirements. Some will match the requirements; others will be elaborations of 
requirements, such as definitions of all error messages in response to a requirement to display error 
messages; others will be implementation related, such as decisions about what software units and 
logic to use to satisfy the requirements. 

Developer . An organization that develops software products (“develops” may include new 
development, modification, reuse, reengineering, maintenance, or any other activity that results in 
software products). 

Document/documentation . A collection of data, regardless of the medium on which it is recorded, 
that generally has permanence and can be read by humans or machines. 

Evaluation . The process of determining whether an item or activity meets specified criteria. 

Firmware . The combination of a hardware device and computer instructions and/or computer data 
that reside as read-only software on the hardware device. 


8 



Hardware item . An aggregation of hardware that satisfies an end use function and is designated for 
purposes of specification, interfacing, qualification testing, configuration management, or other 
purposes. 

Independent verification and validation (IV&V) . Systematic evaluation of software products and 
activities by an agency that is not responsible for developing the product or performing the activity 
being evaluated. IV&V is not within the scope of this standard. 

Interface . In software development, a relationship among two or more entities (such as software item 
to software item, software item to hardware item, software item to user, software unit to software 
unit, etc.) in which the entities share, provide, or exchange data. An interface is not a software item, 
software unit, or other system component; it is a relationship among them. 

Joint review . A process or meeting involving representatives of both the acquirer and the developer, 
during which project status, software products, and/or project issues are examined and discussed. 

Key performance parameter (KPP) T Those minimum attributes or characteristics considered most 
essential for an effective military capability. Failure to meet a KPP threshold can be cause for the 
system concept to be reevaluated or the program to be reassessed or terminated. KPPs are validated 
by the Joint Requirements Oversight Council (JROC). 

Maintainability . Prior to the start of a mission, this defines the probability that the system can be 
retained in or returned to a mission capable state within a specified period of time when a failure 
occurs. Pre-mission maintainability supports availability. During a mission, this defines the 
probability that the system can be retained in or returned to an operational state within a specified 
period of time when a failure occurs. Mission maintainability supports dependability. 

Maintenance (of software) ^ See software maintenance. 

Maintenance organization . The organization that is responsible for modifying and otherwise 
sustaining the software after transition from the development organization. 

Non-deliverable software product . A software product that is not required by the contract to be 
delivered to the acquirer or other designated recipient. 

Process . An organized set of activities performed for a given purpose; for example, the software 
development process. 

Qualification testing . Testing performed to demonstrate to the acquirer that a system or software item 
meets its specified requirements. 

Reengineering . The process of examining and altering an existing system to reconstitute it in a new 
form. May include reverse engineering (analyzing a system and producing a representation at a 
higher level of abstraction, such as design from code), restructuring (transforming a system from one 


^ This is from the GLOSSARY: Defense Acquisition Acronyms and Terms, Eleventh Edition, September 2003 [3]. 
4 This is based on information from Section 3.1 of J-STD-016-1995 [6]. 


9 



representation to another at the same level of abstraction), redocumentation (analyzing a system and 
producing user or support documentation), forward engineering (using software products derived 
from an existing system, together with new requirements, to produce a new system), retargeting 
(transforming a system to install it on a different target system), and translation (transforming source 
code from one language to another or from one version of a language to another). 

Reliability . This defines the probability that the system will be able to complete the mission without 
failure given the system was available at the start of the mission. Reliability does not account for 
returning the system to a mission capable state (maintainability). 

Requirement . 

(1) A characteristic that a system or software item must possess in order to be acceptable to the 
acquirer. 

(2) A mandatory statement in this standard or another portion of the contract. 

Reusable software product . A software product developed for one use but having other uses, or one 
developed specifically to be usable on multiple projects or in multiple roles on one project. Examples 
include, but are not limited to, COTS software products, acquirer-furnished software products, 
software products in reuse libraries, and pre-existing developer software products. Each use may 
include all or part of the software product and may involve its modification. This term can be applied 
to any software product (for example, requirements, architectures, etc.), not just to software itself. 

Software ^. Computer programs, procedures, and data pertaining to the operation of a computer 
system. Data may include, for example, information in databases, rule bases, configuration data. 
Procedures may include, for example, interpreted scripts. 

Note: Although some definitions of software include documentation, this standard limits the 
definition to computer programs, procedures, and data. 

Software development . A set of activities that results in software products. Software development 
may include new development, modification, reuse, reengineering, maintenance, or any other 
activities that result in software products. 

Software development file (SDF) . A repository for material pertinent to the development of a 
particular body of software. Contents typically include (either directly or by reference) 
considerations, rationale, and constraints related to requirements analysis, design, and 
implementation; developer-internal test information; and schedule and status information. 

Software development library (SDL) . A controlled collection of software, documentation, other 
intermediate and final software products, and associated tools and procedures used to facilitate the 
orderly development and subsequent maintenance of software. 

Software development process . An organized set of activities performed to translate user needs into 
software products. 


5 This is adapted from IEEE Standard Glossary of Software Engineering Terminology. IEEE Std 610.12-1990. September 
28, 1990 [8], 


10 



Software engineering . In general usage, a synonym for software development. As used in this 
standard, a subset of software development consisting of all activities except qualification testing. 

The standard makes this distinction for the sole purpose of giving separate names to the software 
engineering and software test environments. 

Software engineering environment . The facilities, hardware, software, firmware, procedures, and 
documentation needed to perform software engineering. Elements may include but are not limited to 
computer-aided software engineering (CASE) tools, compilers, assemblers, linkers, loaders, operating 
systems, debuggers, simulators, emulators, documentation tools, and database management systems. 

Software item 4 . An aggregation of software that satisfies an end use function and is designated for 
purposes of specification, interfacing, qualification testing, configuration management, or other 
purposes. Software items are selected based on tradeoffs among software function, size, host or 
target computers, developer, support strategies, plans for reuse, criticality, interface considerations, 
need to be separately documented and controlled, and other factors. A software item is comprised of 
one or more software units. A software item is sometimes called a computer software configuration 
item (CSCI). 

Software maintenance 4 . The set of activities that takes place to ensure that software installed for 
operational use continues to perform as intended and fulfill its intended role in system operation. 
Software maintenance includes sustaining support, aid to users, and related activities. 

Software product . Software or associated information created, modified, or incorporated to satisfy a 
contract. Examples include plans, requirements, design, code, databases, test information, and 
manuals. 

Software quality . The ability of software to satisfy its specified requirements. 

Software support . See software maintenance. 

Software system . A system consisting solely of software and possibly the computer equipment on 
which the software operates. 

Software test environment . The facilities, hardware, software, firmware, procedures, and 
documentation needed to perform qualification, and possibly other, testing of software. Elements 
may include but are not limited to simulators, code analyzers, test case generators, and path analyzers, 
and may also include elements used in the software engineering environment. 

Software transition . The set of activities that enables responsibility for software to pass from one 
organization to another. 

Software unit . An element in the design of a software item; for example, a major subdivision of a 
software item, a component of that subdivision, a class, object, module, function, routine, or database. 
Software units may occur at different levels of a hierarchy and may consist of other software units. 
Software units in the design may or may not have a one-to-one relationship with the code and data 
entities (routines, procedures, databases, data files, etc.) that implement them or with the computer 
files containing those entities. A software unit is sometimes called a computer software unit (CSU). 


11 



Support (of software) . See software maintenance. 


Supportability . The degree to which system design characteristics and planned logistics resources 
(including software) meet pre-mission readiness and operational utilization requirements. The 
primary performance requirements that characterize supportability are availability, dependability/ 
reliability, and maintainability. 

Technical performance measure (TPM) . A measurement that indicates progress toward meeting 
critical system characteristics (technical parameters) that are specified in requirements or constrained 
by system design. Technical parameters that are tracked with TPMs have clearly identifiable and 
measurable target and threshold values. Examples of technical parameters, which can be tracked 
using TPMs, are space vehicle weight, space vehicle power, and computer system resource margins 
(e.g., CPU, I/O, memory margins). 

Test . The terms “test” and “testing,” as used in this standard, refer to the activities of verifying that 
the implementation meets the design (unit and integration testing) and verifying that the requirements 
are satisfied (qualification testing). These terms should not be confused with the verification method 
“Test,” which is only one of the four standard methods used for verification (i.e.. Inspection (I), 
Analysis (A), Demonstration (D), and Test (T)). 

Testability . A design characteristic of hardware and software, which allows the status of an item to 
be confidently determined in a timely fashion. 

Transition (of software) . See software transition. 

User . For the purpose of this standard, users include operators of the system in addition to the end 
users of the data produced by the system. 

Work product ^. Any artifact produced by a process. 


6 This is from Capability Maturity Model Integration, Version 1.1, CMU/SEI-2002-TR-012, March 2002, p. 24. [11, 12], 


12 



4. General Requirements 


4.1 Software development process 

The developer shall establish a software development process consistent with contract requirements. 
The software development process shall include the following major activities, which may overlap, 
may be applied iteratively, may be applied differently to various elements of software, and need not 
be performed in the order listed below. The developer’s software development process shall be 
described in the SDP. 

The framework used to organize the major software activities is called the software development life 
cycle model. The developer shall select software life cycle model(s) appropriate to the software 
being developed and shall document the selected software life cycle model(s) in the SDP. A software 
project may have more than one type of software development life cycle model in use for different 
types of software being developed for the contract. 

a) Project planning and oversight (Section 5.1) 

b) Establishing a software development environment (Section 5.2) 

c) System requirements analysis (Section 5.3) 

d) System design (Section 5.4) 

e) Software requirements analysis (Section 5.5) 

f) Software design (Section 5.6) 

g) Software implementation and unit testing (Section 5.7) 

h) Unit integration and testing (Section 5.8) 

i) Software item qualification testing (Section 5.9) 

j) Software/hardware item integration and testing (Section 5.10) 

k) System qualification testing (Section 5.11) 

l) Preparing for software transition to operations (Section 5.12) 

m) Preparing for software transition to maintenance (Section 5.13) 

n) Integral processes: 

1) Software configuration management (Section 5.14) 

2) Software peer reviews and product evaluation (Section 5.15) 

3) Software quality assurance (Section 5.16) 

4) Corrective action (Section 5.17) 

5) Joint technical and management reviews (Section 5.18) 

6) Risk management (Section 5.19) 

7) Software management indicators (Section 5.20) 

8) Security and privacy (Section 5.21) 

9) Subcontractor management (Section 5.22) 

10) Interface with software IV&V agents (Section 5.23) 

11) Coordination with associate developers (Section 5.24) 

12) Improvement of project processes (Section 5.25) 

4.2 General requirements for software development 

The developer shall meet the following general requirements in carrying out the detailed requirements 
in Section 5 of this standard. 


13 



4.2.1 Software development methods 

The developer shall use systematic, documented methods for all software development activities. 
These methods shall be described in the SDP. 

4.2.2 Standards for software products 

The developer shall develop and apply standards for representing requirements, design, code, test 
cases, test procedures, and test results. These standards shall be described in the SDP. 

4.2.3 Traceability 7 

The developer shall perform bi-directional traceability between levels of requirements, between 
requirements and design, between design and the software that implements it, between requirements 
and qualification test information, and between computer hardware resource utilization requirements 
and measured computer hardware resource utilization. The result shall include the applicable 
traceability items of the System/Segment Specification DID, Interface Requirements Specification 
DID, Software Requirements Specification DID, System/Segment Design Description DID, Software 
Design Description DID, Software Test Plan DID, Software Test Description DID, Software Test 
Report (STR) DID, and Software Product Specification DID. (See Section 6.2 for the DID numbers.) 

When requirements are derived in whole or in part from design decisions, then those requirements 
shall be traced to the documentation of those design decisions. 

For the purposes of satisfying the requirements of this paragraph, the traceability “between design and 
the software that implements it” shall encompass all forms of software used to implement the design, 
not just the code. Thus, for example, design traceability to software would include implementation 
such as interpreted command scripts and rule bases, if they were used to implement the design, not 
just traceability to the interpreter or inference engine. 

Note: The intent of this requirement is to trace both upward and downward to: 

1) Ensure that all requirements are implemented and tested, and 

2) Provide information for software maintenance. 

4.2.4 Reusable software products 

The developer shall identify and evaluate reusable software products (examples include COTS, 
software products in reuse libraries, and pre-existing developer software products) for use in fulfilling 
the requirements of the contract. The scope of the search and the criteria to be used for evaluation 
shall be as described in the SDP. Reusable software products that meet the criteria shall be used 
where practical. Appendix B provides candidate criteria for evaluating reusable software products. 
Incorporated software products shall meet the data rights requirements in the contract. 

Note 1: In addition, the developer may be required by the contract to develop software products 
specifically for reuse. 

Note 2: Any requirement that calls for the development of a software product may be met by a 
reusable software product that fulfills the requirement and meets the criteria established in the SDP. 
The reusable software product may be used as-is or modified and may be used to satisfy part or the 
entire requirement. 


7 This is based on information from Section 4.2.3 of J-STD-016-1995 [6], 


14 



Note 3: When a reusable software product to be incorporated is the software itself, some of the 
requirements in this standard may require special inteipretation. Such interpretation should be 
documented in the SDP. 

4.2.5 Assurance of critical requirements 

If a system relies on a computer subsystem (including software and computer hardware) to satisfy 
requirements identified as critical, the developer shall identify those computer hardware and/or 
software items or portions thereof whose failure could lead to violations of those critical 
requirements; develop a strategy, including both test and analyses, to ensure that the requirements, 
design, implementation, and operating procedures for the identified computer hardware and/or 
software minimize or eliminate the potential for such violations; record the strategy in the SDP; 
implement the strategy; and produce evidence, as part of the required computer hardware and 
software products, that the assurance strategy has been successfully carried out. The developer shall 
identify and develop strategies for the following types of critical requirements: 

a) Safety: those software items or portions thereof whose failure could lead to a hazardous 
system state (one that could result in unintended death, injury, loss of property, or 
environmental harm); 

b) Security: those software items or portions thereof whose failure could lead to a breach of 
system security; 

c) Privacy protection: those software items or portions thereof whose failure could lead to a 
breach of system privacy protection; 

d) Dependability, reliability, maintainability, and availability; 

e) Other mission-critical requirements (e.g., derived from Key Performance Parameters 
(KPPs)) as agreed to by the acquirer and developer. 

4.2.6 Computer hardware resource utilization 

The developer shall analyze requirements and design constraints concerning computer hardware 
resource utilization (such as maximum allowable use of processor capacity, memory capacity, 
input/output device capacity, auxiliary storage device capacity, and communications/network 
equipment capacity). The developer shall allocate computer hardware resources, monitor the 
utilization of these resources, and reallocate or identify the need for additional resources as necessary 
to meet requirements and design constraints. The allocated resource utilizations shall be managed as 
Technical Performance Measures (TPMs). 

4.2.7 Recording rationale 

The developer shall record rationale for key decisions made in specifying, designing, implementing, 
and testing the software. The rationale shall include trade-offs considered, analysis methods, and 
criteria used to make the decisions. The rationale shall be recorded in documents, code comments, or 
other media that will transition to the maintenance organization (contractor or government). The 
meaning of “key decisions” and the approach for providing the rationale shall be described in the 
SDP. 

4.2.8 Access for acquirer review 

The developer shall provide the acquirer or its authorized representative access to developer and 
subcontractor facilities, including the software engineering and test environments, for review of 
software products and activities. 


15 



16 



5. Detailed Requirements 


The order of the requirements in this section is not intended to specify the order in which they must 
be carried out. Some activities may not be applicable to the project or contracted effort. Many of the 
activities may be ongoing at one time; different software products may proceed at different paces; and 
activities specified in early subsections may depend on input from activities in later subsections. If 
the software is developed in multiple builds, some activities may be performed in every build, others 
may be performed only in selected builds, and activities and software products may not be complete 
until several or all builds are accomplished. Non-mandatory notes throughout Section 5 tell how to 
interpret each activity on a project involving multiple builds. A project involving a single build will 
accomplish all required activities in that build. 

5.1 Project planning and oversight 

The developer shall perform project planning and oversight in accordance with the following 
requirements. 

Note: If a system or software item is developed in multiple builds, planning for each build should be 
interpreted to include: 

a) Overall planning for the contract, 

b) Detailed planning for the current build, and 

c) Planning for future builds to a level of detail compatible with the information available. 

5.1.1 Software development planning 

The developer shall develop and record plans for conducting the activities required by this standard 
and by other software-related requirements in the contract. This planning shall be consistent with 
system-level planning and shall include all applicable items in the Software Development Plan (SDP) 
template in Appendix H. 

The developer shall define, and document in the SDP, the artifacts and other information to be 
developed and recorded to satisfy the intent and spirit of the contents of the software-related products 
required by this standard. In addition, the developer shall define and document in the SDP, the 
artifacts and other information to be developed and recorded to prepare all software-related CDRL 
items required by the contract. When any product (or portion thereof) described in the DIDs 
referenced in this standard is required as a CDRL item by the contract, the DID for the CDRL item, as 
tailored for the contract, shall take precedence over the DID contents referenced in this standard. 

Note: The wording here and throughout this standard is designed to: 

1) Emphasize that the development and recording of planning and engineering information is an 
intrinsic part of the software development process, to be performed regardless of whether a 
deliverable is required; 

2) Use the DID as a checklist of items to be covered in the planning or engineering activity; and 

3) Permit representations other than traditional documents for recording the information (e.g., 
computer-aided software engineering (CASE) tools). 


17 



5.1.2 Software item test planning 

The developer shall develop and record plans for conducting software item qualification testing. This 
planning shall include all applicable items in the Software Test Plan (STP) DID, as defined in the 
SDP (see Section 5.1.1). The software test planning shall address all verification methods (i.e., 
Inspection (I), Analysis (A), Demonstration (D), and Test (T)) and levels (e.g., unit, item, subsystem, 
element, segment, or system) necessary to fully verify the software requirements, including the 
software interface requirements. 

Note: See Section 6.2 for the STP DID number. 

5.1.3 System test planning 

The developer shall participate in developing and recording plans for conducting system qualification 
testing. The system test planning shall address all verification methods (i.e., Inspection (I), Analysis 
(A), Demonstration (D), and Test (T)) and verification levels (e.g., unit, build, item, subsystem, 
element, segment, or system) necessary to fully verify the system requirements, including the system 
interface requirements. 

Note 1: System qualification testing in this paragraph is to be interpreted to mean the verification of 
all levels of requirements higher in the specification tree than the software requirements (e.g., 
subsystem, element, segment, or system). 

5.1.4 Planning for software transition to operations 

The developer shall develop and record plans for performing software installation and training at the 
user sites specified in the contract. This planning shall include all applicable items in the Software 
Installation Plan (SIP) DID, as defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the SIP DID number. 

5.1.5 Planning for software transition to maintenance 

The developer shall identify all software development resources that will be needed by the 
maintenance organization to fulfill the support concept specified in the contract. The developer shall 
develop and record plans identifying these resources and describing the approach to be followed for 
transitioning deliverable items to the maintenance organization. This planning shall include all 
applicable items in the Software Transition Plan (STrP) DID, as defined in the SDP (see Section 
5.1.1). 

Note: See Section 6.2 for the STrP DID number. 

5.1.6 Following and updating plans 

Following acquirer approval of any of the plans in this section, the developer shall conduct the 
relevant activities in accordance with the plan. The developer’s management shall review the 
software development process at intervals specified in the SDP to ensure that the process complies 
with the contract and adheres to the plans. With the exception of developer-internal scheduling and 
related staffing information, updates to plans shall be subject to acquirer approval. 

5.2 Establishing a software development environment 

The developer shall establish, control, and maintain a software development environment in 
accordance with the following requirements. The developer shall analyze the adequacy of the 
planned software engineering and test environments and shall document the results of that analysis in 
the SDP. 


18 



Note: If a system or software item is developed in multiple builds, establishing the software 
development environment in each build is interpreted to mean establishing the environment needed to 
complete that build. 

5.2.1 Software engineering environment 

The developer shall establish, control, and maintain a software engineering environment to perform 
the software engineering effort. The developer shall ensure that each element of the environment 
performs its intended functions. 

5.2.2 Software integration and test environment 

The developer shall establish, control, and maintain a software test environment to perform 
integration and qualification testing of software. The developer shall ensure that each element of the 
environment performs its intended functions. 

5.2.3 Software development library 

The developer shall establish, control, and maintain a software development library (SDL) to 
facilitate the orderly development and subsequent maintenance of software. The SDL may be an 
integral part of the software engineering and test environments. The developer shall maintain the 
SDL throughout the contract period of performance. 

5.2.4 Software development files 

The developer shall establish, control, and maintain a Software Development File (SDF) for each 
software unit or logically related group of software units, for each software item, for each build (when 
using iterative life cycle models), and, as applicable, for logical groups of software items, for 
subsystems, and for the overall system. The developer shall record information about the 
development of the software in appropriate SDFs and shall maintain the SDFs throughout the contract 
period of performance. 

5.2.5 Non-deliverable software 

The developer may use non-deliverable software in the development of deliverable software as long 
as the operation and maintenance of the deliverable software after delivery to the acquirer do not 
depend on the non-deliverable software or the acquirer has or can obtain the same software. The 
developer shall ensure that all non-deliverable software used performs its intended functions. 

5.3 System requirements analysis 

The developer shall participate in system requirements analysis in accordance with the following 
requirements. 

Note: If a system is developed in multiple builds, its requirements may not be fully defined until the 
final build. The developer’s planning will identify the subset of system requirements to be defined in 
each build and the subset to be implemented in each build. System requirements analysis for a given 
build should be interpreted to mean defining the system requirements so identified for that build. 


19 



5.3.1 Analysis of user input 8 

The developer shall participate in analyzing user input provided by the acquirer to gain an 
understanding of the user needs. This input may take the form of need statements, surveys, 
problem/change reports, feedback on prototypes, interviews, or other user input or feedback. 

Note: This requirement is intended to ensure that all interested parties maintain ongoing 
communications regarding user needs throughout the development of the system. Interested parties 
include, but are not limited to, the user, acquirer, developer, and maintenance and test organizations. 

5.3.2 Operational concept 

The developer shall participate in defining and recording the operational concept for the system. The 
result shall include all applicable items in the Operational Concept Description (OCD) DID, as 
defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the OCD DID number. 

5.3.3 System requirements 

Based on the analysis of user needs, the operational concepts, and other considerations, the developer 
shall participate in defining and recording the requirements to be met by the system and the methods 
to be used to ensure that each requirement has been met. The result shall include all applicable items 
in the System/Subsystem Specification (SSS) DID, as defined in the SDP (see Section 5.1.1). 
Depending on CDRL provisions, requirements concerning system interfaces may be included in the 
SSS or in the Interface Requirements Specifications (IRSs). 

Note 1: If a system consists of segments/subsystems, the activity in 5.3.3 is intended to be performed 
iteratively with the activities in 5.4 (System design) to define system requirements, design the system 
and identify its segments/subsystems, define the requirements for those segments/subsystems, design 
the segments/subsystems and identify their components, and so on. 

Note 2: See Section 6.2 for the SSS and IRS DID numbers. 

5.4 System design 

The developer shall participate in system design in accordance with the following requirements. 

Note: If a system is developed in multiple builds, its design may not be fully defined until the final 
build. The developer’s planning will identify the portion of the system design to be defined in each 
build. System design for a given build is interpreted to mean defining the portion of the system 
design identified for that build. 

5.4.1 System-wide design decisions 

The developer shall participate in defining and recording system-wide design decisions (that is, 
decisions about the system’s behavioral design and other decisions affecting the selection and design 
of system components). The result shall include all applicable items in the system-wide design 
section of the System/Subsystem Design Description (SSDD) DID, as defined in the SDP (see 
Section 5.1.1). 

Note 1: Design decisions remain at the discretion of the developer unless converted to requirements. 
The developer is responsible for fulfilling all requirements and demonstrating this fulfillment through 
qualification testing (see Sections 5.9, 5.11). Design decisions act as developer-internal 


8 The Note is based on information from Section 5.3.1 of J-STD-016-1995 [6], 


20 



“requirements,” to be implemented, imposed on subcontractors, if applicable, and confirmed by 
developer-internal testing, but their fulfillment need not be demonstrated to the acquirer. 

Note 2: See Section 6.2 for the SSDD DID number. 

5.4.2 System architectural design 9 

The developer shall participate in defining and recording the architectural design of the system 
(identifying the components of the system, their interfaces, and a concept of interaction among them) 
and the traceability between the system components and system requirements. The result shall 
include all applicable items in the architectural design and traceability sections of the 
System/Subsystem Design Description (SSDD) DID, as defined in the SDP (see Section 5.1.1). 

Note 1: For conciseness, this section is written in terms of organizing a system into components. 
However, this should be interpreted to cover organizing a system into segments/subsystems, 
organizing a segment/subsystem into hardware items, software items, and manual operations, or other 
variations as appropriate. 

Note 2: See Section 6.2 for the SSDD DID number. 

5.5 Software requirements analysis 

Based on the analysis of system requirements, the system design, and other considerations, the 
developer shall define and record the software requirements to be met by each software item, the 
methods and levels for verifying each requirement, and the traceability between the software item 
requirements and their parent requirements. The result shall include all applicable items in the 
Software Requirements Specification (SRS) DID and Interface Requirements Specification (IRS) 
DID, as defined in the SDP (see Section 5.1.1). 

Note 1: If a software item is developed in multiple builds, its requirements may not be fully defined 
until the final build. The developer’s planning will identify the subset of each software item’s 
requirements to be defined in each build and the subset to be implemented in each build. Software 
requirements analysis for a given build should be interpreted to mean defining the software item 
requirements so identified for that build. 

Note 2: See Section 6.2 for the SRS and IRS DID numbers. 

5.6 Software design 

The developer shall perform software design in accordance with the following requirements. 

Note: If a software item is developed in multiple builds, its design may not be fully defined until the 
final build. Software design in each build is interpreted to mean the design necessary to meet the 
software item requirements to be implemented in that build. 

5.6.1 Software item-wide design decisions 

The developer shall define and record software item-wide design decisions (that is, decisions about 
the software item’s behavioral design and other decisions affecting the selection and design of the 
software units comprising the software item). The result shall include all applicable items in the 
software item-wide design section of the Software Design Description (SDD) DID, as defined in the 
SDP (see Section 5.1.1). Design pertaining to interfaces and databases shall be included in Interface 


9 Note 1 is based on information from Section 5.4.2 of J-STD-016-1995 [6], 


21 



Design Descriptions (IDDs) and Database Design Descriptions (DBDDs), as defined in the SDP (see 
Section 5.1.1). 

Note: See Section 6.2 for the SDD, IDD, and DBDD DID numbers. 

5.6.2 Software item architectural design 

The developer shall define and record the architectural design of each software item (identifying the 
software units comprising the software item, their interfaces, and a concept of interaction among 
them) and the traceability between the software units and the software item requirements. The result 
shall include all applicable items in the architectural design and traceability sections of the Software 
Design Description (SDD) DID, as defined in the SDP (see Section 5.1.1). Designs pertaining to 
interfaces and databases shall be included in Interface Design Descriptions (IDDs) and Database 
Design Descriptions (DBDDs), as defined in the SDP (see Section 5.1.1). 

Note 1: Software units may be made up of other software units and may be organized into as many 
levels as are needed to represent the software item architecture. For example, a software item may be 
divided into three software units, each of which is divided into additional software units, and so on. 

Note 2: See Section 6.2 for the SDD, IDD, and DBDD DID numbers. 

5.6.3 Software item detailed design 

The developer shall develop and record a description of each software unit. The result shall include 
all applicable items in the detailed design section of the Software Design Description (SDD) DID, as 
defined in the SDP (see Section 5.1.1). Designs pertaining to interfaces shall include all items in the 
Interface Design Description (IDD), as defined in the SDP (see Section 5.1.1). Designs of software 
units that are databases or are service units that access or manipulate databases shall include all items 
in the Database Design Description (DBDD), as defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the SDD, IDD, or DBDD DID numbers. 

5.7 Software implementation and unit testing 

The developer shall perform software implementation and unit testing in accordance with the 
following requirements. 

Note 1: If a software item is developed in multiple builds, software implementation and unit testing 
of that software item might not be completed until the final build. Software implementation and unit 
testing in each build should be interpreted to include those units, or parts of units, needed to meet the 
software item requirements to be implemented in that build. 

Note 2: The terms “unit test” and “unit testing” refer to the activity of verifying the correctness of the 
unit implementation. The use of the words “test” or “testing” in this paragraph should not be 
confused with the verification method of Test. The activity of unit testing may require the use of all 
verification methods (i.e., Inspection (I), Analysis (A), Demonstration (D), and Test (T)). 

5.7.1 Software implementation 

The developer shall develop and record software corresponding to each software unit in the software 
item design. This activity shall include, as applicable, coding computer instructions and data 
definitions, building databases, populating databases and other data files with data values, and other 
activities needed to implement the design. 


22 



Note: Software units in the design may or may not have a one-to-one relationship with the code and 
data entities (routines, procedures, databases, data files, etc.) that implement them or with the 
computer files containing those entities. 

5.7.2 Preparing for unit testing 

The developer shall establish test cases (in terms of inputs, expected results, and evaluation criteria), 
test procedures, and test data for testing the software corresponding to each software unit. The test 
cases shall cover the unit’s design, including, as a minimum, the correct execution of all statements 
and branches; all error and exception handling; all software unit interfaces including limits and 
boundary conditions; start-up, termination, and restart (when applicable); and all algorithms. Legacy 
reuse software shall be unit tested for all modified reuse software units, for all reuse software units 
where the track record indicates potential problems (even if the reuse units have not been modified), 
and all critical reuse software units (even if the reuse units have not been modified). The developer 
shall record this information in the appropriate SDFs. 

5.7.3 Performing unit testing 

The developer shall test the software corresponding to each software unit. The testing shall be in 
accordance with the unit test cases and procedures. 

5.7.4 Revision and retesting 

Based on the results of unit testing, the developer shall make all necessary revisions to the software, 
perform all necessary retesting, and update the SDFs and other software products as needed, based on 
the results of unit testing. Regression testing of affected software unit test cases shall be performed 
after any modification to previously tested software. 

5.7.5 Analyzing and recording unit test results 

The developer shall analyze the results of unit testing and shall record the test and analysis results in 
appropriate SDFs. 

5.8 Unit integration and testing 

The developer shall perform unit integration and testing in accordance with the following 
requirements. 

Note 1: Unit integration and testing means integrating the software corresponding to two or more 
software units, testing the resulting software to ensure that it works together as intended, and 
continuing this process until all software in each software item is integrated and tested. The last stage 
of this testing is developer-internal software item testing. Since units may consist of other units, 
some unit integration and testing may take place during unit testing. The requirements in this section 
are not meant to duplicate those activities. 

Note 2: If a software item is developed in multiple builds, unit integration and testing of that software 
item will not be completed until the final build. Unit integration and testing in each build is 
interpreted to mean integrating software developed in the current build with other software developed 
in that and previous builds, and testing the results. 

Note 3: As stated in Note 1, the term “integration and test” refers to the activity of verifying the 
correct functioning of an integrated collection of units. The use of the words “test” or “testing” in this 
paragraph should not be confused with the verification method of Test. The activity of unit 


23 



integration and testing may require the use of all verification methods (i.e., Inspection (I), Analysis 
(A), Demonstration (D), and Test (T)). 

5.8.1 Preparing for unit integration and testing 

The developer shall establish test cases (in terms of inputs, expected results, and evaluation criteria), 
test procedures, and test data for conducting unit integration and testing. The test cases shall cover, as 
a minimum, the correct execution of all interfaces between software units, including limit and 
boundary conditions; integrated error and exception handling across the software units under test; all 
end-to-end functional capabilities through the software units under test; all software requirements 
allocated to the software units under test; performance testing, including operational input and output 
data rates and timing and accuracy requirements; stress testing, including worst-case scenario(s); 
start-up, termination, and restart (when applicable); fault detection, isolation, and recovery handling 
(e.g., fault tolerance, fail over, data capture and reporting); and resource utilization measurement 
(e.g., CPU, memory, storage, bandwidth). Whenever possible, software unit integration testing shall 
be performed on the target hardware in a configuration as close as possible to the operational 
configuration. All reuse software, including modified and unmodified legacy reuse and COTS 
software, shall undergo software unit integration testing. The developer shall record this information 
in the appropriate SDFs. 

5.8.2 Performing unit integration and testing 

The developer shall perform unit integration and testing. The testing shall be in accordance with the 
unit integration test cases and procedures. 

5.8.3 Revision and retesting 

The developer shall make all necessary revisions to the software, perform all necessary retesting, and 
update the SDFs and other software products as needed, based on the results of unit integration and 
testing. Regression testing of affected software integration test cases shall be performed after any 
modification to previously tested software. 

5.8.4 Analyzing and recording unit integration and test results 

The developer shall analyze the results of unit integration and testing and shall record the test and 
analysis results in appropriate SDFs. 

5.9 Software item qualification testing 

The developer shall perform software item qualification testing in accordance with the following 
requirements. 

Note 1: Software item qualification testing is performed to demonstrate to the acquirer that software 
item requirements have been met. It covers the software item requirements in Software Requirements 
Specifications (SRSs) and in associated Interface Requirements Specifications (IRSs). This testing 
contrasts with developer-internal software item testing, performed as the final stage of unit integration 
and testing. 

Note 2: If a software item is developed in multiple builds, its software item qualification testing will 
not be completed until the final build for that software item, or possibly until later builds involving 
items with which the software item is required to interface. Software item qualification testing in 
each build is inteipreted to mean planning and performing tests of the current build of each software 
item to ensure that the software item requirements to be implemented in that build have been met. 


24 



Note 3: As stated in Note 1, the term “software item qualification testing” refers to the activity of 
verifying that the software requirements have been met, including the software interface 
requirements. The use of the words “test” or “testing” in this paragraph should not be confused with 
the verification method of Test. The activity of qualification testing may require the use of all 
verification methods (i.e., Inspection (I), Analysis (A), Demonstration (D), and Test (T)). 

5.9.1 Independence in software item qualification testing 

The person(s) responsible for qualification testing of a given software item shall not be the persons 
who performed detailed design or implementation of that software item. This does not preclude 
persons who performed detailed design or implementation of the software item from contributing to 
the process, for example, by contributing test cases that rely on knowledge of the software item’s 
internal implementation. 

5.9.2 Testing on the target computer system 

Software item qualification testing shall be performed using the target hardware. The target hardware 
used for software qualification testing shall be as close as possible to the operational target hardware 
and shall be in a configuration as close as possible to the operational configuration. 

5.9.3 Preparing for software item qualification testing 

The developer shall define and record the test preparations, test cases, and test procedures to be used 
for software item qualification testing and the traceability between the test cases, test procedure steps, 
and the software item and software interface requirements. The result shall include all applicable 
items in the Software Test Description (STD) DID, as defined in the SDP (see Section 5.1.1). The 
developer shall prepare the test data needed to carry out the test cases and provide the acquirer 
advance notice of the time and location of software item qualification testing. The software 
qualification test cases shall cover, as a minimum, verification of all software requirements under 
conditions that are as close as possible to those that the software will encounter in the operational 
environment (e.g., operational data constants, operational input and output data rates, operational 
scenarios, target hardware configurations); verification of all software interface requirements, using 
the actual interfaces wherever possible or high-fidelity simulation of the interfaces where not 
possible; verification of all software specialty engineering requirements (e.g., supportability, 
testability, dependability/reliability/maintainability/ availability, safety, security, and human systems 
integration, as applicable), including in particular verification of software reliability requirements and 
fault detection, isolation, and recovery requirements; stress testing, including worst-case scenarios; 
and resource utilization measurement (e.g., CPU, memory, storage, bandwidth). All software 
requirements shall be verified by software qualification testing whether they are satisfied by COTS, 
reuse (modified or unmodified) or newly developed software. 

Note: See Section 6.2 for the STD DID number. 

5.9.4 Dry run of software item qualification testing 

The developer shall dry run the software item test cases and procedures to ensure that they are 
complete and accurate and that the software is ready for witnessed testing. The developer shall record 
the results of this activity in appropriate SDFs and shall update the software item test cases and 
procedures as appropriate. 


25 



5.9.5 Performing software item qualification testing 

The developer shall perform software item qualification testing of each software item. The testing 
shall be in accordance with the software item test cases and procedures. Regression testing of the 
affected software qualification test cases shall be performed after any modification to previously 
tested software. 

5.9.6 Revision and retesting 

The developer shall make necessary revisions to the software, provide the acquirer advance notice of 
retesting, conduct all necessary retesting, and update the SDFs and other software products as needed, 
based on the results of software item qualification testing. 

5.9.7 Analyzing and recording software item qualification test results 

The developer shall analyze and record the results of software item qualification testing. The results 
shall include all applicable items in the Software Test Report (STR) DID, as defined in the SDP (see 
Section 5.1.1). The developer shall document and maintain a cumulative record of the verification 
status (fully verified, partially verified, not verified) of all software requirements, including software 
interface requirements, for all verification testing events, all verification methods (i.e., Inspection (I), 
Analysis (A), Demonstration (D), and Test (T)), and all levels in the verification testing hierarchy 
(e.g., unit, item, build, item, subsystem, segment, or system). 

Note: See Section 6.2 for the STR DID number. 

5.10 Software/hardware item integration and testing 

The developer shall participate in software/hardware item integration and testing activities in 
accordance with the following requirements. 

Note 1: Software/hardware item integration and testing means integrating software items with 
interfacing hardware items and software items, testing the resulting groupings to determine whether 
they work together as intended, and continuing this process until all software items and hardware 
items in the system are integrated and tested. The last stage of this testing is developer-internal 
system testing. 

Note 2: If a system or software item is developed in multiple builds, software/hardware item 
integration and testing may not be complete until the final build. Software/hardware item integration 
and testing in each build is inteipreted to mean integrating the current build of each software item 
with the current build of other software items and hardware items and testing the results to ensure that 
the system requirements to be implemented in that build have been met. 

Note 3: As stated in Note 1, the term “software/hardware item integration and testing” refers to the 
activity of verifying the correct functioning of an integrated collection of hardware and software 
items or portions thereof. The use of the words “test” or “testing” in this paragraph should not be 
confused with the verification method of Test. The activity of unit integration and testing may 
require the use of all verification methods (i.e., Inspection (I), Analysis (A), Demonstration (D), and 
Test (T)). 

5.10.1 Preparing for software/hardware item integration and testing 

The developer shall participate in developing and recording test cases (in terms of inputs, expected 
results, and evaluation criteria), test procedures, and test data for conducting software/hardware item 
integration and testing. The test cases shall cover all aspects of the system-wide and system 
architectural design. The developer shall record software-related information in appropriate SDFs. 


26 



The software/hardware integration test cases shall cover, as a minimum, the correct execution of all 
software-to-software and software-to-hardware interfaces among the software and hardware items 
under test, including limit and boundary conditions; integrated error and exception handling across 
the software and hardware items under test; all end-to-end functional capabilities through the software 
and hardware items under test; all software requirements allocated to the software and hardware items 
under test; performance testing, including operational input and output data rates and timing and 
accuracy requirements; stress testing, including worst-case scenario(s); start-up, termination, and 
restart (when applicable); fault detection, isolation, and recovery handling (e.g., fault tolerance, fail 
over, data capture and reporting); and resource utilization measurement (e.g., CPU, memory, storage, 
bandwidth). Software/hardware integration testing shall be performed using the target hardware that 
is as close as possible to the operational target hardware and is in a configuration as close as possible 
to the operational configuration. All reuse software, including modified and unmodified legacy reuse 
and COTS software, shall undergo software/hardware item integration testing. 

5.10.2 Performing software/hardware item integration and testing 

The developer shall participate in software/hardware item integration and testing. The testing shall be 
in accordance with the software/hardware integration test cases and procedures. 

5.10.3 Revision and retesting 

The developer shall make necessary revisions to the software, participate in all necessary retesting, 
and update the appropriate SDFs and other software products as needed, based on the results of 
software/hardware item integration and testing. Regression testing of affected software/hardware 
integration test cases shall be performed after any modification to previously tested software. 

5.10.4 Analyzing and recording software/hardware item integration and test results 

The developer shall participate in analyzing the results of software/hardware item integration and 
testing. Software-related analysis and test results shall be recorded in appropriate SDFs. 

5.11 System qualification testing 

The developer shall participate in system qualification testing in accordance with the following 
requirements. 

Note 1: System qualification testing is performed to demonstrate to the acquirer that system 
requirements have been met. It covers requirements in the system specification, the segment 
specifications (if applicable) and all other levels of requirements between the system and segment 
specifications and the software requirements specifications in the specification tree (e.g., element 
specifications, subsystem specifications, etc.), including interface requirements at all of these levels. 
This testing contrasts with developer-internal system testing, performed as the final stage of 
software/hardware item integration and testing. 

Note 2: If a system is developed in multiple builds, qualification testing of the completed system will 
not occur until the final build. System qualification testing in each build is interpreted to mean 
planning and performing tests of the current build of the system to ensure that the system 
requirements to be implemented in that build have been met. 

Note 3: As stated in Note 1, the term “system qualification testing” refers to the activity of verifying 
that the system requirements have been met, including the system interface requirements. The use of 
the words “test” or “testing” in this paragraph should not be confused with the verification method of 
Test. The activity of qualification testing may require the use of all verification methods (i.e., 
Inspection (I), Analysis (A), Demonstration (D), and Test (T)). 


27 



5.11.1 Independence in system qualification testing 

The person(s) responsible for fulfilling the requirements in this section shall not be the persons who 
performed detailed design or implementation of software in the system. This does not preclude 
persons who performed detailed design or implementation of software in the system from 
contributing to the process, for example, by contributing test cases that rely on knowledge of the 
system’s internal implementation. 

5.11.2 Testing on the target computer system 

System qualification testing shall include testing using the operational target hardware in the 
operational configuration. 

5.11.3 Preparing for system qualification testing 

The developer shall participate in developing and recording the test preparations, test cases, and test 
procedures to be used for system qualification testing and the traceability between the test cases, test 
procedure steps, and the system requirements. The developer shall participate in preparing the test 
data needed to carry out the test cases and in providing the acquirer advance notice of the time and 
location of system qualification testing. 

5.11.4 Dry run of system qualification testing 

The developer shall participate in dry running the system test cases and procedures to ensure that they 
are complete and accurate and that the system is ready for witnessed testing. The developer shall 
record the software-related results of this activity in appropriate SDFs and shall participate in 
updating the system test cases and procedures as appropriate. 

5.11.5 Performing system qualification testing 

The developer shall participate in system qualification testing. Thi s participation shall be in 
accordance with the system test cases and procedures. 

5.11.6 Revision and retesting 

The developer shall make necessary revisions to the software, provide the acquirer advance notice of 
retesting, participate in all necessary retesting, and update the SDFs and other software products as 
needed, based on the results of system qualification testing. 

5.11.7 Analyzing and recording system qualification test results 

The developer shall participate in analyzing and recording the results of system qualification testing. 

5.12 Preparing for software transition to operations 

The developer shall prepare for software use (including transition to operations) in accordance with 
the following requirements. 

Note: If software is developed in multiple builds, the developer’s planning will identify what 
software, if any, is to be fielded (i.e., distributed) to users in each build and the extent of fielding (for 
example, full fielding or fielding to selected evaluators only). Preparing for software use in each 
build is inteipreted to include those activities necessary to carry out the fielding plans for that build. 


28 



5.12.1 Preparing the executable software 

The developer shall prepare the executable software for each user site, including any batch files, 
command files, data files, or other software files needed to install and operate the software on its 
target computer(s). The result shall include all applicable items in the executable software section of 
the Software Product Specification (SPS) DID, as defined in the SDP (see Section 5.1.1). 

Note 1: To contractually require only the executable software (delaying delivery of source files and 
associated support information to a later build), the acquirer can use the SPS DID, tailoring out all but 
the executable software section of that DID. 

Note 2: See Section 6.2 for the SPS DID number. 

5.12.2 Preparing version descriptions for user sites 

The developer shall identify and record the exact version of software prepared for each user site. The 
information shall include all applicable items in the Software Version Description (SVD) DID, as 
defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the SVD DID number. 

5.12.3 Preparing user manuals 

The developer shall prepare user manuals in accordance with the following requirements. 

Note: Few, if any, systems will need all of the manuals in this section. The intent is for the acquirer, 
with input from the developer, to determine which manuals are appropriate for a given system and to 
require the development of only those manuals. The manuals specified in this standard can be 
substituted with commercial or other manuals that contain the required information. The manuals in 
this section are normally developed in parallel with software development, ready for use in software 
item testing. 

5.12.3.1 Software user manuals 

The developer shall identify and record information needed by hands-on users of the software 
(persons who will both operate the software and make use of its results). The information shall 
include all applicable items in the Software User Manual (SUM) DID, as defined in the SDP (see 
Section 5.1.1). 

Note: See Section 6.2 for the SUM DID number. 

5.12.3.2 Computer operation manuals 

The developer shall identify and record information needed to operate the computers on which the 
software will run. The information shall include all applicable items in the Computer Operation 
Manual (COM) DID, as defined by the SDP (see Section 5.1.1). 

Note 1: This paragraph only applies to computers without commercial operations manuals or to 
computers whose commercial operations manuals are not adequate. Examples of computer hardware 
for which this paragraph may apply are the processors in special test equipment or flight testbeds. 

Note 2: See Section 6.2 for the COM DID number. 

5.12.4 Installation at user sites 

The developer shall: 

a) Install and check out the executable software at the user sites specified in the contract. 


29 



b) Provide training to users as specified in the contract. 

c) Provide other assistance to user sites as specified in the contract. 

5.13 Preparing for software transition to maintenance 

The developer shall prepare for transition of software to maintenance in accordance with the 
following requirements. 

Note 1: If software is developed in multiple builds, the developer’s planning should identify what 
software, if any, is to be transitioned to the maintenance organization in each build. Preparing for 
software transition in each build is interpreted to include those activities necessary to carry out the 
transition plans for that build. 

Note 2: Software maintenance may be performed by the same organization that developed the 
software or by a different organization (e.g., a government maintenance organization, another 
development contractor, or another organization within the company that developed the software). 

5.13.1 Preparing the executable software 

The developer shall prepare the executable software to be transitioned to the maintenance site, 
including any batch files, command files, data files, or other software files needed to install and 
operate the software on its target computer(s). The result shall include all applicable items in the 
executable software section of the Software Product Specification (SPS) DID, as defined by the SDP 
(see Section 5.1.1). 

Note: See Section 6.2 for the SPS DID number. 

5.13.2 Preparing source files 

The developer shall prepare the source files to be transitioned to the maintenance site, including any 
batch files, command files, data files, or other files needed to regenerate the executable software. The 
result shall include all applicable items in the source file section of the Software Product Specification 
(SPS) DID, as defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the SPS DID number. 

5.13.3 Preparing version descriptions for the maintenance site 

The developer shall identify and record the exact version of software prepared for the maintenance 
site. The information shall include all applicable items in the Software Version Description (SVD) 
DID, as defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the SVD DID number. 

5.13.4 Preparing the “as built” software item design and related information 

The developer shall update the design description of each software item to match the approved “as 
built” software and shall define and record: the methods to be used to verify copies of the software, 
the measured computer hardware resource utilization for the software item, other information needed 
to maintain the software, and traceability between the software item’s source files and software units 
and between the computer hardware resource utilization measurements and the software item 
requirements concerning them. The result shall include all applicable items in the qualification, 
software maintenance, and traceability sections of the Software Product Specification (SPS) DID, as 
defined in the SDP (see Section 5.1.1). 


30 



Note: See Section 6.2 for the SPS DID number. 


5.13.5 Updating the system/subsystem design description 

The developer shall participate in updating the system design description to match the approved “as 
built” system. The result shall include all applicable items in the System/Segment Design Description 
(SSDD) DID, as defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the SSDD DID number. 

5.13.6 Updating the software requirements 10 

The developer shall participate in updating the software and interface requirements for each software 
item to match the approved “as built” system. The result shall include all applicable items in the 
Software Requirements Specification (SRS) DID and in the Interface Requirements Specification 
(IRS) DID, as defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the SRS and IRS DID numbers. 

5.13.7 Updating the system requirements 11 

The developer shall participate in updating the system and interface requirements to match the 
approved “as built” system. The result shall include all applicable items in the System/Segment 
Specification (SSS) DID and in the Interface Requirements Specification (IRS) DID, as defined in the 
SDP (see Section 5.1.1). 

Note: See Section 6.2 for the SSS and IRS DID numbers. 

5.13.8 Preparing maintenance manuals 

The developer shall prepare maintenance manuals in accordance with the following requirements. 

Note: Not all systems will need the manuals in this section. The intent is for the acquirer, maintainer, 
and developer to determine which manuals are appropriate for a given system and to require the 
development of only those manuals. The manuals specified in this standard can be substituted with 
commercial or other manuals that contain the required information. The manuals in this section 
supplement the System/Segment Design Description (SSDD) and the Software Product Specifications 
(SPSs), which serve as the primary sources of information for software maintenance. The user 
manuals cited in Section 5.12.3 are also useful to maintenance personnel. 

5.13.8.1 Computer programming manuals 

The developer shall identify and record information needed to program the computers on which the 
software was developed or on which it will run. The information shall include all applicable items in 
the Computer Programming Manual (CPM) DID, as defined in the SDP (see Section 5.1.1). 

Note 1: This paragraph applies only to newly developed computer hardware, which does not have 
commercial programming manuals available, or to computer hardware for which the commercial 
programming manuals are not adequate. 

Note 2: See Section 6.2 for the CPM DID number. 


10 This is based on infonnation from Section 5.13.6 of J-STD-016-1995 [6]. 

11 This is based on infonnation from Section 5.13.7 of J-STD-016-1995 [6], 


31 



5.13.8.2 Firmware support manuals 

The developer shall identify and record information needed to program and reprogram any firmware 
devices in which the software will be installed. The information shall include all applicable items in 
the Firmware Support Manual (FSM) DID, as defined in the SDP (see Section 5.1.1). 

Note: See Section 6.2 for the FSM DID number. 

5.13.9 Transition to the designated maintenance site 

The developer shall: 

a) Install and check out the deliverable software in the maintenance environment designated in 
the contract. 

b) Demonstrate to the acquirer that the deliverable software can be regenerated 
(compiled/linked/loaded into an executable product) and maintained using commercially 
available, acquirer-owned, or contractually deliverable software and hardware designated in 
the contract or approved by the acquirer. 

c) Provide training to the maintenance organization as specified in the contract. 

d) Provide other assistance to the maintenance organization as specified in the contract. 

5.14 Software configuration management 

The developer shall perform software configuration management in accordance with the following 
requirements. 

Note: If a system or software item is developed in multiple builds, the software products of each 
build may be refinements of, or additions to, software products of previous builds. Software 
configuration management in each build should be understood to take place in the context of the 
software products and controls in place at the start of the build. 

5.14.1 Configuration identification 

The developer shall participate in selecting software items, as performed under system architectural 
design in Section 5.4.2, shall identify the entities to be placed under configuration control, and shall 
assign a project-unique identifier to each software item and each additional entity to be placed under 
configuration control. These entities shall include the software products to be developed or used 
under the contract and the elements of the software development environment. The identification 
scheme shall be at the level at which entities will actually be controlled, for example, computer files, 
electronic media, documents, software units, hardware items, software items. The identification 
scheme shall include the version/ revision/release status of each entity. 

5.14.2 Configuration control 

The developer shall establish and implement procedures designating the levels of control each 
identified entity must pass through (for example, author control, acquirer control); the persons or 
groups with authority to authorize changes and to make changes at each level (for example, the 
programmer/analyst, the software lead, the project manager, the acquirer); and the steps to be 
followed to request authorization for changes, process change requests, track changes, distribute 
changes, and maintain past versions. Changes that affect an entity already under acquirer control 
shall be proposed to the acquirer in accordance with contractually established forms and procedures, 
if any. 


32 



Note: The levels of control to be implemented are dependent upon the entity to be placed under 
configuration control. Thus, an SRS generally passes through author level control, software 
configuration management level control, and program level control. Software code, on the other 
hand, generally has more levels of control, for example: individual developer, software integration 
(team leader level), software build integration, software qualification, and segment/system control. 

The SDP defines the levels of control to be used for each entity to be placed under configuration 
control, in addition to the roles, responsibilities and procedures for each level. 

5.14.3 Configuration status accounting 

The developer shall prepare and maintain records of the configuration status of all entities that have 
been placed under any level of configuration control above the individual author/developer level. 
These records shall be maintained for the life of the contract. They shall include, as applicable, the 
current version/revision/release of each entity, a record of changes to the entity since being placed 
under any level of configuration control above the individual author/developer level, and the status of 
problem/change reports affecting the entity. 

Note: The degree of formality of the configuration status accounting may differ at different levels of 
configuration control. 

5.14.4 Configuration audits 12 

The developer shall periodically conduct audits of all entities that have been placed under any level of 
configuration control above the individual author/developer level. These audits shall ensure that each 
entity only incorporates all approved changes (and no other changes) scheduled for inclusion at the 
time of the audit. 

Note: The degree of formality of the configuration audits may differ at different levels of 
configuration control. 

5.14.5 Packaging, storage, handling, and delivery 

The developer shall establish and implement procedures for the packaging, storage, handling, and 
delivery of deliverable software products. The developer shall maintain master copies of delivered 
software products for the duration of the contract. 

5.15 Software peer reviews and product evaluations 

The developer shall perform software peer reviews and product evaluation in accordance with the 
following requirements. 

5.15.1 Software peer reviews 

The developer shall perform peer reviews of software work products in accordance with the following 
requirements. 

Note: Planning for peer reviews of software work products is part of software development planning 
(see Section 5.1.1) and is documented in the SDP. 

5.15.1.1 Prepare for software peer reviews 

The developer shall perform peer reviews on the software work products as specified in the SDP. For 
each peer review: 


12 This is based on infonnation from Section 5.14.4 of J-STD-016-1995 [6], 


33 



a) The developer shall determine what type of peer review will be conducted on the software 
work product. 

b) The developer shall identify key reviewers who must participate in the peer review. 

c) The developer shall ensure that the software work product satisfies the peer review entry 
criteria prior to distribution of peer review materials. 

d) Each reviewer shall prepare by reviewing the software work product prior to conducting the 
peer review. 

5.15.1.2 Conduct peer reviews 

a) The developer shall identify and document defects and other issues in the software work 
product. 

b) The developer shall record and collect the results of the peer review, including action items. 

c) The developer shall ensure that the exit criteria for the peer review are satisfied. 

5.15.1.3 Analyze peer review data 

The developer shall analyze data about preparation, conduct, and results of the peer reviews. 

5.15.2 Software product evaluations 

The developer shall perform software product evaluation in accordance with the following 
requirements. 

Note 1: If a system or software item is developed in multiple builds, the software products of each 
build are evaluated in the context of the objectives established for that build. A software product that 
meets those objectives can be considered satisfactory even though it is missing information 
designated for development in later builds. 

Note 2: Planning for software product evaluations is part of software development planning (see 
Section 5.1.1) and is documented in the SDP. 

Note 3: It is not the intention of Sections 5.15.1 and 5.15.2 to require two separate processes, one for 
peer reviews and one for software product evaluations, although the developer may choose to satisfy 
the requirements of the standard in this manner. Software products evaluations may be accomplished 
via the peer review process as long as the requirements for product evaluations specified in the 
following subparagraphs are satisfied. 

5.15.2.1 In-process and final software product evaluations 

The developer shall perform in-process evaluations of the software products generated in carrying out 
the requirements of this standard. In addition, the developer shall perform a final evaluation of each 
deliverable software product before its delivery. The software products to be evaluated, minimum 
criteria to be used, and definitions for those criteria are given in Appendix D. 

5.15.2.2 Software product evaluation records 

The developer shall prepare and maintain records of each software product evaluation. These records 
shall be maintained for the duration of the contract. Problems in software products under any level of 
configuration control above the individual author/developer level shall be handled as described in 
Section 5.17 (Corrective action). 


34 



5.15.2.3 Independence in software product evaluation 

The persons responsible for evaluating a software product shall not be the persons who developed the 
product. This does not preclude the persons who developed the software product from taking part in 
the evaluation (for example, as participants in a peer review of the product.). 

5.16 Software quality assurance 

The developer shall perform software quality assurance in accordance with the following 
requirements. 

Note: If a system or software item is developed in multiple builds, the activities and software 
products of each build are evaluated in the context of the objectives established for that build. An 
activity or software product that meets those objectives can be considered satisfactory even though it 
is missing aspects designated for later builds. Planning for software quality assurance is included in 
software development planning (see Section 5.1.1). 

5.16.1 Software quality assurance evaluations 

The developer shall conduct ongoing evaluations of software development processes, software 
products and work products, and software services to ensure: 

a) Adherence of the designated, performed processes to the applicable process descriptions, 
standards, and procedures in accordance with the contract and with the SDP; 

b) Adherence of the designated work products and services to the applicable process 
descriptions, standards, and procedures in accordance with the contract and with the SDP; 
and 

c) That each software product required by this standard or by other contract provisions exists 
and has undergone software product evaluations and peer reviews, testing (for those products 
where testing is applicable), and corrective action (for all identified problems), as required by 
this standard and by other contract provisions. 

5.16.2 Software quality assurance records 

The developer shall establish and maintain records of each software quality assurance activity. These 
records shall be maintained for the duration of the contract. 

5.16.3 Independence in software quality assurance 

The persons responsible for conducting software quality assurance evaluations shall not be the 
persons who developed the software product or work product, performed the process or service, or are 
responsible for the software product, work product, or process. The persons responsible for assuring 
compliance with the contract shall have the resources, responsibility, authority, and organizational 
freedom to permit objective software quality assurance evaluations and to initiate and verify 
corrective actions. 

5.16.4 Software quality assurance noncompliance issues 

The developer shall: 

a) Communicate quality issues and ensure resolution of noncompliance issues with the staff and 
managers; 

b) Use an established escalation mechanism to ensure that the appropriate level of management 
can resolve the issues; and 


35 



c) Track noncompliance issues to resolution. Noncompliance issues in software products or 
work products under any level of configuration control above the individual author/developer 
level shall be handled as described in Section 5.17 (Corrective action system). 

5.17 Corrective action 

The developer shall perform corrective action in accordance with the following requirements. 

5.17.1 Problem/change reports 

The developer shall prepare a problem/change report to describe each problem detected in software 
entities under any level of configuration control above the individual author/developer level and each 
problem in activities required by the contract or described in the SDP. The problem/change report 
shall describe the problem, the corrective action needed, and the actions taken to date. These reports 
shall serve as input to the corrective action system. 

Note: The degree of formality of the problem/change reports may differ at different levels of 
configuration control. 

5.17.2 Corrective action system 

The developer shall implement a corrective action system for handling each problem detected in 
software entities under any level of configuration control above the individual author/developer level 
and each problem in activities required by the contract or described in the SDP. The system shall 
meet the following requirements: 

a) Inputs to the system shall consist of problem/change reports. 

b) The system shall be closed-loop, ensuring that all detected problems are promptly reported 
and entered into the system, action is initiated on them, resolution is achieved, status is 
tracked, and records of the problems are maintained for the duration of the contract. 

c) Each problem shall be classified by category and severity, as a minimum. Guidance is 
provided in Appendix C. 

d) Analysis shall be performed to detect trends in the problems reported. 

e) Corrective actions shall be evaluated to determine whether problems have been resolved, 
adverse trends have been reversed, and changes have been correctly implemented without 
introducing additional problems. 

Note: The degree of formality of the problem/change reports may differ at different levels of 
configuration control. 

5.18 Joint technical and management reviews 

The developer shall plan and take part in joint (acquirer/developer) technical and management 
reviews in accordance with the following requirements. 

Note: If a system or software item is developed in multiple builds, the types of joint reviews held and 
the criteria applied will depend on the objectives of each build. Software products that meet those 
objectives can be considered satisfactory even though they are missing information designated for 
development in later builds. 


36 



5.18.1 Joint technical reviews 

The developer shall plan and take part in joint technical reviews at locations and dates proposed by 
the developer and approved by the acquirer. These reviews shall be attended by persons with 
technical knowledge of the software products to be reviewed. The reviews shall focus on in-process 
and final software products, rather than materials generated especially for the review. The reviews 
shall have the following objectives: 

a) Review evolving software products, using as minimum criteria the software product 
evaluation criteria in Appendix D; review and demonstrate proposed technical solutions; 
provide insight and obtain feedback on the technical effort; surface and resolve technical 
issues. 

b) Review project status; surface near- and long-term risks regarding technical, cost, and 
schedule issues. 

c) Arrive at agreed-upon mitigation strategies for identified risks, within the authority of those 
present. 

d) Identify risks and issues to be raised at joint management reviews. 

e) Ensure ongoing communication between acquirer and developer technical personnel. 

5.18.2 Joint management reviews 

The developer shall plan and take part in joint management reviews at locations and dates proposed 
by the developer and approved by the acquirer. These reviews shall be attended by persons with 
authority to make cost and schedule decisions and shall have the following objectives. Examples of 
such reviews are identified in Appendix E. 

a) Keep management informed about project status, directions being taken, technical 
agreements reached, and overall status of evolving software products. 

b) Resolve issues that could not be resolved at joint technical reviews. 

c) Arrive at agreed-upon mitigation strategies for near- and long-term risks that could not be 
resolved at joint technical reviews. 

d) Identify and resolve management-level issues and risks not raised at joint technical reviews. 

e) Obtain commitments and acquirer approvals needed for timely accomplishment of the 
project. 

5.19 Risk management 

The developer shall perform risk management throughout the software development process. The 
developer shall identify, analyze, and prioritize the areas of the software development project that 
involve potential technical, cost, or schedule risks; develop strategies for managing those risks; record 
the risks and strategies as described in the SDP; and implement the strategies in accordance with the 
plan. 

5.20 Software management indicators 

The developer shall perform software measurement throughout the software life cycle in accordance 
with ISO 15939 [9]. The developer shall plan the measurement process by identifying and defining a 
set of software management indicators, including the data to be collected, the methods to be used to 
interpret and apply the data, and the reporting mechanism. The developer shall record this 
information in the SDP or a Software Metrics Plan. The developer shall perform the measurement 


37 



process by collecting, interpreting, applying, and reporting on those indicators at regular intervals, as 
described in the SDP or Software Metrics Plan. Management indicators selected for use in managing 
the software development process are at the discretion of the contractor. Candidate indicators are 
given in Appendix F. Additional guidance is provided in the book “Practical Software Measurement 
Objective Information for Decision Makers ” by John McGarry et al, Addison Wesley, 2001 [10]. 

If the acquirer requires specific software measures to be collected and reported, the developer shall 
incorporate these measures into their selected set of management indicators as part of their software 
measurement process. 

5.21 Security and privacy 

The developer shall meet the security and privacy requirements specified in the contract. These 
requirements may affect the software development effort, the resulting software products, or both. 

5.22 Subcontractor management 

If subcontractors are used, the developer shall include in subcontracts all contractual requirements 
necessary to ensure that software products are developed in accordance with prime contract 
requirements. 

5.23 Interface with software IV&V agents 

The developer shall interface with the software Independent Verification and Validation (IV&V) 
agent(s) as specified in the contract. 

5.24 Coordination with associate developers 

The developer shall coordinate with associate developers, working groups, and interface groups as 
specified in the contract. 

5.25 Improvement of project processes 

The developer shall periodically assess the processes used on the project to determine their suitability, 
efficiency and effectiveness, as described in the SDP. Based on these assessments, the developer 
shall identify any necessary and beneficial improvements to the process, shall identify these 
improvements to the acquirer in the form of proposed updates to the SDP and, if approved, shall 
implement the improvements on the project. 


38 



6. Notes 


6.1 Intended use 

This section contains information of a general or explanatory nature that may be helpful, but is not 
mandatory. 

6.2 Data Item Descriptions (DIDs) 

The following DIDs must be listed, as applicable, on the Contract Data Requirements List (CDRL) in 
order to have the product delivered under the contract. 


DID Title 

DID Number 

Reference Section 

Software Development Plan (SDP) 

Use Appendix H 

5.1.1, 5.1.2, 5.1.4, 5.1.5, 5.1.6, 5.2, 5.3.2, 5.3.3, 

5.4.1, 5.4.2, 5.5, 5.6.1, 5.6.2, 5.6.3, 5.9.3, 5.9.7, 

5.12.1, 5.12.2, 5.12.3.1, 5.12.3.2, 5.13.1, 5.13.2, 
5.13.3, 5.13.4, 5.13.5, 5.13.6, 5.13.8.1, 5.13.8.2, 

5.14.2, 5.15.1, 5.15.1.1, 5.15.2, 5.16, 5.16.1, 
5.17.1, 5.17.2, 5.19, 5.20, 5.25 

Software Test Plan (STP) 

DI-IPSC-81438A 

5.1.2, 5.1.3 

Software Installation Plan (SIP) 

DI-IPSC-81428A 

5.1.4 

Software Transition Plan (STrP) 

DI-IPSC-81429A 

5.1.5 

Operational Concept Description (OCD) 

DI-IPSC-81430A 

5.3.2 

System/Segment Specification (SSS) 

DI-IPSC-81431A 

5.3.3, 5.13.7 

Interface Requirements Specification (IRS) 

DI-IPSC-81434A 

5.3.3, 5.5, 5.9, 5.13.6, 5.13.7 

System/Segment Design Description (SSDD) 

DI-IPSC-81432A 

5.4.1,5.4.2,5.13.5,5.13.8 

Interface Design Description (IDD) 

DI-IPSC-81436A 

5.6.1, 5.6.2, 5.6.3 

Software Requirements Specification (SRS) 

DI-IPSC-81433A 

5.5,5.9,5.11,5.13.6,5.14.2 

Software Design Description (SDD) 

DI-IPSC-81435A 

5.6.1, 5.6.2, 5.6.3 

Database Design Description (DBDD) 

DI-IPSC-81437A 

5.6.1, 5.6.2, 5.6.3 

Software Test Description (STD) 

DI-IPSC-81439A 

5.9.3 

Software Test Report (STR) 

DI-IPSC-81440A 

5.9.7, 5.11.7 

Software Product Specification (SPS) 

DI-IPSC-81441A 

5.12.1,5.13.1,5.13.2,5.13.4,5.13.8 

Software Version Description (SVD) 

DI-IPSC-81442A 

5.12.2,5.13.3 

Software User Manual (SUM) 

DI-IPSC-81443A 

5.12.3.1 

Computer Operation Manual (COM) 

DI-IPSC-81446A 

5.12.3.2 

Computer Programming Manual (CPM) 

DI-IPSC-81447A 

5.13.8.1 

Firmware Support Manual (FSM) 

DI-IPSC-81448A 

5.13.8.2 


39 



6.3 Relationship between standard and CDRL 

If the CDRL calls for a DID different from the one named in corresponding paragraph(s) of this 
standard, all references to the DID in the standard should be interpreted to mean the one in the CDRL. 

6.4 Delivery of tool contents 

Depending on contract provisions, the developer may be permitted to satisfy CDRL requirements by 
delivering: 

1) A repository or database containing the information specified in the cited DID; 

2) A means of accessing that repository or database, such as a C ASE tool, if not already 
available to the recipients designated on the CDRL; and 

3) A hard-copy or electronically stored table of contents, specifying how and where to access 
the information required in each paragraph of the DID. 

6.5 Tailoring guidance 

This standard and its DIDs are applied at the discretion of the acquirer. In each application, the 
standard and DIDs should be tailored to the specific requirements of a particular program, program 
phase, or contractual structure. Care should be taken to eliminate tasks that add unnecessary costs 
and data that do not add value to the process or the product. Tailoring for the standard takes the form 
of deletion of activities, alteration of activities to more explicitly reflect the application to a particular 
effort, or addition of activities to satisfy program requirements. This tailoring is specified in the 
SOW or Compliance Documents section of the contract. Tailoring for the DIDs consists of deleting 
requirements for unneeded information and making other changes, such as combining two documents 
under one cover, that do not increase the required workload. DID tailoring for deliverables is 
specified in the CRDL. 

6.6 Related standardization documents 

Other standardization documents may be imposed or quoted in the SOW or Compliance Documents 
section of the contract to supplement the requirements in this standard. The acquirer should use 
caution to ensure that supplemental standards are appropriate to the project and that any conflicts 
among them or with this standard are identified and resolved. See Recommended Software Standards 
for Space Systems, Aerospace Report No. TOR-2004(3909)-3406 [2] for information on other 
software standards. 


40 



6.7 Subject term (key word) listing 

The following list of key words may be used to catalog or characterize key topics in this standard. 


Builds/incremental development 
Computer software configuration item 
Database 

Joint technical/management reviews 

Operational concept 

Reusable software 

Risk management 

Security/privacy 

Software 

Software configuration management 
Software development 


Software documentation 
Software implementation 
Software maintenance 
Software management indicators 
Software product evaluation 
Software quality assurance 
Software requirements analysis 
Software safety 
Software testing 
Software unit 
Tailoring 


41 



42 



Appendix A. List of acronyms 


A.1 Scope 

This appendix provides a list of acronyms used in this standard. This appendix is not a mandatory 
part of the standard. The information provided is intended for guidance only. 

A.2 Acronyms 

CASE Computer-Aided Software Engineering 

CDRL Contract Data Requirements List 

COM Computer Operation Manual 

COTS Commercial Off-The-Shelf 

CSCI Computer Software Configuration Item 

CSU Computer Software Unit 

CPM Computer Programming Manual 

DBDD Database Design Description 

DID Data Item Description 

DoD Department of Defense 

FSM Firmware Support Manual 

HW Hardware 

IDD Interface Design Description 

IPT Integrated Product Team 

IRS Interface Requirements Specification 

IV&V Independent Verification and Validation 

JROC Joint Requirements Oversight Council 

KPP Key Performance Parameter 

OCD Operational Concept Description 

SDD Software Design Description 

SDF Software Development File 

SDL Software Development Library 

SDP Software Development Plan 

SIP Software Installation Plan 

SOW Statement of Work 

SPS Software Product Specification 

SRS Software Requirements Specification 

SSDD System/Segment Design Description 

SSS System/Segment Specification 

STD Software Test Description 

STP Software Test Plan 

STR Software Test Report 

STrP Software Transition Plan 

SUM Software User Manual 

SVD Software Version Description 

SW Software 

TPM Technical Performance Measure 

WBS Work Breakdown Structure 


A-l 



A-2 



Appendix B. Interpreting this standard for incorporation of COTS and 

reusable software products 


B.1 Scope 

This appendix inteiprets this standard when applied to the incorporation of reusable software 
products. This appendix is an informative part of the standard. It is provided as an aid in using this 
standard. 

B.2 Evaluating reusable software products 

Examples of criteria for evaluating reusable software products are: 

a) Ability to provide required capabilities and meet required constraints 

1) Ability to satisfy requirements 

2) Ability to achieve necessary performance, especially with realistic operational 
workloads 

3) Appropriateness of algorithms in the COTS/reusable software product for use in the 
new system 

4 ) As evidenced by characterization/stress testing within the system context to 
determine capabilities and performance 

b) Ability to provide required protection (safety, security, and privacy) 

1) Provided inherently in the COTS or reusable software product, or 

2) Able to be provided around the COTS/reusable software product by system design 
and implementation 

c) Reliability/maturity 

1) As evidenced by established track record 

2) As evidenced by prototype evaluation within the system context 

d) Testability 

1) As evidenced by the ability to identify and isolate faults 

e) Operability 

1) Suitability of the COTS/reusable software product’s implied operations concept to 
the operations concept of the new system 

f) COTS or reusable software product supplier viability 

1) Compatibility of COTS or reusable software product supplier’s future direction with 
program needs (including both software and platform emphasis) 

2) Supplier long-term commitment to COTS or reusable software product 

3) Supplier long-term business prospects 

4 ) Type of supplier support available 

5) Quality of supplier support available 

g) Suitability for incorporation into the new system architecture 

1) Compatible software architecture and design features 

2) Absence of obsolete technologies 

3) Need for re-engineering and/or additional code development (e.g., wraps, “glue” 
code) 

4 ) Compatibility among the set of reusable software products 

5) As evidenced by prototyping within the system context (e.g., to determine 
compatibility, wraps, “glue” code) 

h) Ability to remove or disable features/capabilities not required in the new system 

1) Impact if those features cannot be removed/disabled or are not removed/disabled 


B-l 



2) As evidenced by prototyping within the system context 

i) Interoperability with other system and system-external elements 

1) Compatibility with system interfaces 

2) Adherence to standards (e.g., open systems interface standards) 

3) Ability to interface with legacy systems 

j) Availability of personnel knowledgeable about the reusable software product 

1) Training required 

2) Hiring required 

3) Vendor or third-party support required 

k) Availability and quality of documentation and source files 

1) Completeness 

2) Accuracy 

l) Acceptability of reusable software product licensing and data rights 

1) Restrictions on copying/distributing the reusable software product or documentation 

2) License or other fees applicable to each copy 

3) Acquirer’s usage and ownership rights, especially to the source code 

a) Ability to place source code in escrow against the possibility of the 

vendor/developer going out of business 

4) Warranties available 

5) Absence of unacceptable restrictions in standard license (e.g., export restrictions, 
expiring keys) 

m) Supportability 

1) Suitability of the COTS/reusable software product’s support paradigm (e.g., 

distribution, installation) to the support concept of the new system, especially for 
mobile or remote sites 

n) Ability to make changes, including: 

1) Likelihood the software product will need to be changed 

2) Feasibility/difficulty of accomplishing that change, when changes are to be made by 
the program reusing the software product 

a) Quality of design, code and documentation 

b) Need for re-engineering and/or restructuring 

3) Feasibility/difficulty of accomplishing that change, when changes must be made by 
the vendor or product developer (e.g., for COTS or proprietary software) 

a) Priority of changes required by this program versus other changes being made 

b) Likelihood that the changed version will continue to be maintained by the 
vendor/developer 

c) Likelihood of being able to modify future versions to include changes 

d) Impact on life cycle costs 

e) Impact if the current version is not maintained by the vendor/developer or if 
changes are not able to be incorporated into future versions 

o) Impacts of upgrades to COTS or reusable software products 

1) Frequency of COTS/reusable software product upgrades/modifications being made 
by the vendor/developer (i.e., a completely new version or upgrade patches to the 
existing version being released) after a particular version has been incoiporated into 
the system 

2) Feasibility/difficulty of incorporating the new version of the COTS/reusable software 
product into the system 

3) Impact if the new version is not incoiporated 


B-2 



4) Ability of the new architecture to support the evolution of COTS/reusable software 
products 

p) Compatibility of planned upgrades of COTS or reusable software products with software 

development plans and schedules 

1) Compatibility of planned upgrades with build content and schedules 

2) Impact on development costs and schedule to incoiporated upgrades 

3) Dependencies among COTS and reusable software products 

a) Potential for an incompatible set of COTS and/or reusable software products 

b) Potential for schedule delays until all dependent COTS and/or reusable software 
products are upgraded 

q) Criticality of the functionality provided by the COTS or reusable software product 

1) Availability of alternate source(s) for the functionality 

r) Short- and long-term cost impacts of using the COTS or reusable software product 

1) Amount of management reserve needed to handle uncertainties 

a) For example, less COTS/reusable software product usable; more newly 
developed software required; COTS/reusable software product limitations 
identified 

s) Technical, cost, and schedule risks and tradeoffs in using the COTS or reusable software 
product 

1) Ability to tolerate COTS or reusable software product problems beyond the 
program’s control at any point in the system life cycle 

2) Ability to incoiporate continuous evolution of COTS or reusable software products 
during development and maintenance 

B.3 Interpreting this standard’s activities for reusable software products 

The following rules apply in inteipreting this standard: 

a) Any requirement that calls for the development of a software product may be met by a 
reusable software product that fulfills the requirement and meets the criteria established in the 
SDP. The reusable software product may be used as-is or modified and may be used to 
satisfy part or the entire requirement. 

b) When a reusable software product to be incorporated is the software itself, some of the 
requirements in this standard may require special interpretation. Such interpretation should 
be documented in the SDP. 


B-3 



B-4 



Appendix C. Category and severity classifications for problem reporting 


C.1 Scope 

This appendix contains guidance for a category and severity classification scheme to be applied to 
each problem submitted to the corrective action system. This appendix is an informative part of the 
standard. The developer may use alternate category and severity schemes, as described in the SDP. 
Additional guidance may be found in IEEE Std 1044, IEEE Standard Classification for Software 
Anomalies [7]. 

C.2 Classification by category 

It is recommended the software problems be categorized by the products in which they occur and the 
activities in which the problems are injected and discovered. 

a) Figure C.2-1 provides examples of categories for classifying problems found in software 
products. 

b) Figure C.2-2 provides examples of categories for classifying problems by the software 
activity in which the problem is injected and the activity in which the problem is discovered. 


Category 

Applies to problems in: 

a. 

Plans 

One of the plans developed for the project 

m 

Concept 

The operational concept 

c. 

Requirements 

The system or software requirements 

d. 

Design 

The design of the system or software 

e. 

Code 

The software code 

f. 

Database/data file 

A database or data file 

g- 

Test information 

Test plans, test descriptions, or test reports 

a 

Manuals 

The user, operator, or support manuals 

i. 

Other 

Other software products 


Figure C.2-1 Example categories of software products 


C-l 

























Section 

Activity Categories 

5.1 

Project planning and oversight 

5.2 

Establishing a software development environment 

5.3 

System requirements analysis 

5.4 

System design 

5.5 

Software requirements analysis 

5.6 

Software design 

5.7 

Software implementation and unit testing 

5.8 

Unit integration and testing 

5.9 

Software item qualification testing 

5.10 

Software/hardware item integration and testing 

5.11 

System qualification testing 

5.12 

Preparing for software transition to operations 

5.13 

Preparing for software transition to maintenance 

5.14 

Software configuration management 

5.15 

Software peer reviews and product evaluation 

5.16 

Software quality assurance 

5.17 

Corrective action 

5.18 

Joint technical and management reviews 

5.19 

Risk management 

5.20 

Software management indicators 

5.21 

Security and privacy 

5.22 

Subcontractor management 

5.23 

Interface with software IV&V agents 

5.24 

Coordination with associate developers 

5.25 

Improvement of project processes 


Figure C.2-2 Example categories of software activities 


C-2 























































C.3 Classification by severity 

Figure C.3-1 provides an example of a scheme for classifying problems by severity. 


Severity 

Applies if a problem could: 

1 

a. Prevent the accomplishment of an operational or mission essential capability 

b. Jeopardize safety, security, or other requirement designated “critical” 

2 

a. Adversely affect the accomplishment of an operational or mission essential 
capability and no work-around solution is known 

b. Adversely affect technical, cost, or schedule risks to the project or to life cycle 
support of the system, and no work-around solution is known 

3 

a. Adversely affect the accomplishment of an operational or mission essential 
capability but a work-around solution is known 

b. Adversely affect technical, cost, or schedule risks to the project or to life cycle 
support of the system, but a work-around solution is known 

4 

a. Result in user/operator inconvenience or annoyance but does not affect a 
required operational or mission essential capability 

b. Result in inconvenience or annoyance for development or maintenance 
personnel, but does not prevent the accomplishment of those responsibilities 

5 

Any other effect 


Figure C.3-1 Example scheme for classifying problems by severity 


C-3 

















C-4 



Appendix D. Software product evaluations 


D.1 Scope 

This appendix identifies the software products that are to undergo software product evaluations, 
identifies the criteria to be used for each evaluation, and contains a default set of definitions for the 
evaluation criteria. This appendix is a mandatory part of the standard, subject to the following 
conditions: 

1) These requirements may be tailored by the acquirer; 

2) The developer may use alternate criteria or definitions if approved by the acquirer; and 

3) If the development of a given software product has been tailored out of the standard, the 
requirement to evaluate that product does not apply. 

D.2 Required evaluations 

Figure D.3-1 identifies the software products that are to undergo software product evaluations and 
states the criteria to be applied to each one. Each software product and criterion is labeled for 
purposes of identification and tailoring. For convenience, they may be treated as subsections of this 
section (referring to the first criterion, for example, as D.2.l.a). The software products are expressed 
in lower case letters to convey that they are generic products, not necessarily in the form of hard-copy 
documents. Evaluations of system-level products are to be interpreted as participation in these 
evaluations. Some of the criteria are subjective. Because of this, there is no requirement to prove that 
the criteria have been met; the requirement is to perform the evaluations using these criteria and to 
identify possible problems for discussion and resolution. 

D.3 Criteria definitions 

The following subsections provide definitions for the criteria in Figure D.3-1 that may not be self- 
explanatory. The criteria are listed in alphabetical order, matching as closely as possible the wording 
used in Figure D.3-1. 

D.3.1 Accurately describes (an item) 

This criterion, applied to user/operator/programmer instructions and to the “as built” design and 
version descriptions, means that the instructions or descriptions are correct depictions of the software 
or other item described. 

D.3.2 Adequate test cases, procedures, data, results 

Test cases are adequate if they cover all applicable requirements or design decisions and specify the 
inputs to be used, the expected results, and the criteria to be used for evaluating those results. Test 
procedures are adequate if they specify the steps to be followed in carrying out each test case. Test 
data are adequate if they enable the execution of the planned test cases and test procedures. Test or 
dry run results are adequate if they describe the results of all test cases and show that all criteria have 
been met, possibly after revision and retesting. 

D.3.3 Consistent with indicated product(s) 

This criterion means that: 


D-l 



1) No statement or representation in one software product contradicts a statement or 
representation in the other software products; 

2) A given term, acronym, or abbreviation means the same thing in all of the software products; 
and 

3) A given item or concept is referred to by the same name or description in all of the software 
products. 

D.3.4 Contains all applicable information 

This criterion uses the software product contents described in the SDP for the required contents of the 
software products that are not deliverable. This criterion uses the DIDs, as tailored for the contract, to 
specify the required content of deliverable software products. The formatting specified in the DID 
(required structure and numbering) is not relevant to this evaluation. The SDP describes the artifacts 
and other information to be developed and recorded for each product required by this standard (see 
Section 5.1.1). 

D.3.5 Covers (a given set of items) 

A software product “covers” a given set of items if every item in the set has been dealt with in the 
software product. For example, a plan covers the SOW if every provision in the SOW is dealt with in 
the plan; a design covers a set of requirements if every requirement has been dealt with in the design; 
a test plan covers a set of requirements if every requirement is the subject of one or more tests. 
“Covers” corresponds to the downward traceability (for example, from requirements to design) in the 
requirement, design, and test planning/description products. 

D.3.6 Feasible 

This criterion means that, based upon the knowledge and experience of the evaluator, a given 
concept, set of requirements, designs, tests, etc. violates no known principles or lessons learned that 
would render it impossible to carry out. 

D.3.7 Follows SDP 

This criterion means that the software product shows evidence of having been developed in 
accordance with the approach described in the SDP. Examples include following design and coding 
standards described in the plan. For the SDP itself, this criterion applies to updates to the initial plan. 

D.3.8 Internally consistent 

This criterion means that: 

1) No two statements or representations in a software product contradict one another; 

2) A given term, acronym, or abbreviation means the same thing throughout the software 
product; and 

3) A given item or concept is referred to by the same name or description throughout the 
software product. 

D.3.9 Meets CDRL requirements, if applicable 

This criterion applies if the software product being evaluated is specified in the contract and has been 
formatted for delivery at the time of evaluation. It focuses on the format, markings, and other 
provisions specified in the contract, rather than on content, covered by other criteria. 


D-2 



D.3.10 Meets SOW, if applicable 

This criterion means that the software product fulfills any SOW provisions regarding it. For example, 
the SOW may place constraints on the operational concept or the design. 

D.3.11 Presents a sound approach 

This criterion means that, based on the knowledge and experience of the evaluator, a given plan 
represents a reasonable way to carry out the required activities. 

D.3.12 Shows evidence that an item under test meets its requirements 

This criterion means that recorded test results show that the item under test either passed all tests the 
first time or was revised and retested until the tests were passed. 

D.3.13 Testable 

A requirement or set of requirements is considered to be testable if an objective and feasible test can 
be designed to determine whether each requirement has been met. 

D.3.14 Understandable 

This criterion means “understandable by the intended audience.” For example, software products 
intended for programmer-to-programmer communication need not be understandable by non¬ 
programmers. A product that correctly identifies its audience and is considered understandable to that 
audience meets this criterion. 


D-3 



Evaluation Criteria 


Software Contains 

Product all applic. 

info in: 


Software 

Development Plan 
(5.1.1) 

a. SDP 
DID* 

Software Test Plan 
(5.1.2,5.13) 

a. STP 
DID* 

Software Installation 
Plan (5.1.4) 

a. SIP 
DID* 

Software Transition 

Plan 

(5.1.5) 

a. STrP 
DID* 

Operational Concept 
(5.3.2) 

a. OCD 
DID* 

System/Segment 

Requirements 

(5.3.3,5.13.7) 

a. SSS 

IRS 

DIDs* 

System-Wide Design 

Decisions 

(5.4.1) 

a. SSDD 
IDD 

DBDD 

DIDs* 

System Architectural 
Design (5.4.2) 

a. SSDD 
IDD 
DIDs* 



Follows 

SDP 

f. 

(Up¬ 

dates) 

f 

f 

f 

f. 

f. 

I. 

f 


Additional Criteria 


g. Covers all activities/deliverables in SOW 

and CDRL 

h. Consistent with other project plans 

i. Presents a sound approach to the 

development _ 

g. Covers all software-related 
qualification activities in the SOW 

h. Covers all requirements for the items 
under test 

i. Consistent with other project plans 

j. Presents a sound approach to the 

testing _ 

g. Covers all user site installation 
activities in the SOW 

h. Consistent with other project plans 

i. Presents a sound approach to the 

installation _ 

g. Covers all transition-related activities 
in the SOW 

h. Consistent with other project plans 

i. Presents a sound approach to the 

transition _ 

g. Feasible 


g. Covers the operational concept 

h. Feasible 

i. Testable 

g. Consistent with system requirements 

h. Feasible 


g. Covers the system requirements 

h. Consistent with the system-wide 
design decisions 

i. Feasible 


Figure D.3-1 Software products and associated evaluation criteria 

As described in the SDP 


D-4 






























































Software 

Product 

Evaluation Criteria 

Contains 
all applic. 
info in: 

Meets 
SOW, if 
applic. 

Meets 
contract, 
if applic. 

Under¬ 

stand¬ 

able 

Intern. 

consis¬ 

tent 

Follows 

SDP 

Additional Criteria 

Software 

Requirements 

(5.5) 

a. SRS 

IRS 

DIDs* 

b. 

c. 

d. 

e. 

f. 

g. Covers system requirements allocated 
to the software item 

h. Feasible 

i. Testable 

Software Item-Wide 
Design Decisions 
(5.6.1) 

a. SDD 
IDD 
DBDD 
DIDs* 

b. 

c. 

d. 

e. 

f. 

g. Consistent with software item 
requirements 

h. Feasible 

Software Item 
Architectural Design 
(5.6.2) 

a. SDD 
IDD 
DIDs* 

b. 

c. 

d. 

e. 

f. 

g. Covers software item requirements 

h. Consistent with software item-wide 
design decisions 

i. Feasible 

Software Item 
Detailed Design 
(5.6.3) 

a. SDD 
IDD 
DBDD 
DIDs* 

b. 

c. 

d. 

e. 

f. 

g. Covers software item requirements 
allocated to each unit 

h. Consistent with software item-wide 
design decisions 

Software 

Implementation 

(5.7.1) 

a. N/A 

b. 

c. 

d. 

e. 

f. 

g. Covers the software item detailed 
design 

Software Item 
Qualification Test 
Descriptions (5.9.3) 

a. STD 
DID* 

b. 

c. 

d. 

e. 

f. 

g. Covers all software item requirements 

Software Item 
Qualification Test 
Results 
(5.9.7) 

a. STR 
DID* 

b. 

c. 

d. 

e. 

f. 

g. Covers all planned software item 
qualification test cases 

h. Shows evidence that the software 
item meets its requirements 

Software Item 
Qualification 

Test Descriptions 
(5.11.3) 

a. STD 
DID* 

b. 

c. 

d. 

e. 

f. 

g. Covers all system requirements 

Systems 

Qualification 

Test Results (5.11.7) 

a. STR 
DID* 

b. 

c. 

d. 

e. 

f. 

g. Covers all planned system 
qualification test cases 

h. Shows evidence the system meets its 
requirements 

Executable Software 
(5.12.1,5.13.1) 

a. N/A 





f. 

g. Meets delivery requirements 

h. All software necessary for execution 
is present 

i. Version exactly matches version that 
passed testing 

j. Deliverable media accurately labeled 

Software Version 

Descriptions 

(5.12.2,5.13.3) 

a. SVD 

DID* 





f. 

g. Accurately identifies the version of 
each software component (file, unit, 
software item, etc.) delivered 

h. Accurately identifies the changes 
incorporated 


Figure D.3-1 Software products and associated evaluation criteria - continued 


As described in the SDP 


D-5 


















































































Software 

Product 

Evaluation Criteria 

Contains 

all 

applic. 
info in: 

Meets 
SOW, if 
applic. 

Meets 
contract, 
if applic. 

Under¬ 

standable 

Intern. 

consis¬ 

tent 

Follows 

SDP 

Additional Criteria 

Software User 

Manuals 

(5.12.3.1) 

a. SUM 

DID* 

b. 

■ 


■ 

f. 

g. Accurately describes software 
installation and use to the intended 
audience of this manual 

Computer Operation 

Manuals 

(5.12.3.4) 

a. COM 
DID* 

b. 




f. 

g. Accurately describes the operational 
characteristics of the computer 

Source Files 
(5.13.2) 

a. SPS 

DID* 





f. 

g. Meets delivery requirements 

h. All required software is present 

i. Version exactly matches version that 
passed testing 

j. Deliverable media accurately labeled 

“As built” Software 
Item Design and 
Related Information 
(5.13.4) 

a. SPS 

DID 4 

b. 

c. 

d. 

e. 

f. 

g. Accurately describes the “as built” 
design of the software item 

h. Accurately describes compilation/build 
procedures 

i. Accurately describes modification 
procedures 

j. Source files cover all units in the 
software item design 

k. Measured resource utilization meets 
software item requirements 

“As built” System/ 
Segment Design 
(5.13.5) 

a. SSDD 
DID 4 

b. 

■ 


■ 

f. 

g. Accurately describes the “as built” 
system design 

Computer 

Programming 

Manuals 

(5.13.8.1) 

a. CPM 
DID* 

b. 

c. 

d. 


f. 

g. Accurately describes the programming 
features of the computer 

Firmware Support 

Manuals 

(5.13.8.2) 

a. FSM 
DID 4 

b. 

■ 


■ 

f. 

g. Accurately describes firmware 
programming features 

Sampling of 

Software 

Development Files 
(5.2.4, 5.7.2, 5.7.4, 
5.7.5,5.8.1,5.83, 

5.8.4, 5.9.4, 5.9.6, 
5.10.1,5.10.3, 

5.10.4, 5.11.4, 

5.11.6) 

a. N/A 

b. 

N/A 

d. 

e. 

f. 

g. Contents are current with the ongoing 
effort 

h. Adequate unit test cases/procedures/ 
data/results 

i. Adequate unit integration test 
cases/procedures/data/results 

j. Adequate software item qualification 
dry run results 

k. Adequate software/hardware item 
integration test cases/procedures/ 
data/results 

l. Adequate system qualification dry run 
results 


Figure D.3-1 Software products and associated evaluation criteria - continued 

As described in the SDP 


D-6 






























































Appendix E. Candidate joint management reviews 


E.1 Scope 

This appendix describes a candidate set of joint management reviews that might be held during a 
software development project. This appendix is not a mandatory part of this standard. The 
information provided is intended for guidance only. 

E.2 Assumptions 

This appendix makes the following assumptions: 

a) The acquirer has reviewed the subject products in advance, and one or more joint technical 
reviews have been held to resolve issues, leaving the joint management review as a forum to 
resolve open issues and reach agreement as to the acceptability of each product. 

b) Any of the reviews may be conducted incrementally, dealing at each review with a subset of 
the listed items or a subset of the system (e.g., segment, element, subsystem, as applicable) or 
software item(s) being reviewed. 

E.3 Candidate reviews 

Given below is a set of candidate joint management reviews that might be held during a software 
development project. There is no intent to require these reviews or to preclude alternatives or 
combinations of these reviews. The objectives supplement those given in 5.18.2. 

E.3.1 Software plan reviews 

These reviews are held to resolve open issues regarding one or more of the following: 

a) Software Development Plan; 

b) Software Test Plan; 

c) Software Installation Plan; 

d) Software Transition Plan. 

E.3.2 Operational concept reviews 

These reviews are held to resolve open issues regarding the operational concept for the system. 

E.3.3 System/Subsystem requirements reviews 

These reviews are held to resolve open issues regarding the specified requirements for the system, 
segment, element, subsystem, etc. 

E.3.4 System/Subsystem design reviews 

These reviews are held to resolve open issues regarding one or more of the following: 

a) The system-wide/segment-wide/element-wide/subsystem-wide/etc. design decisions; 

b) The architectural design of the system/segment/element/subsystem/etc. 


E-l 



E.3.5 Software requirements reviews 

These reviews are held to resolve open issues regarding the specified requirements for a software 
item. 

E.3.6 Software design reviews 

These reviews are held to resolve open issues regarding one or more of the following: 

a) The software item-wide design decisions; 

b) The architectural design of a software item; 

c) The detailed design of a software item or portion thereof (such as a database). 

E.3.7 Test readiness reviews 

These reviews are held to resolve open issues regarding one or more of the following: 

a) The status of the system/segment/element/subsystem/etc. test environment; 

b) The test cases and test procedures to be used for software item qualification testing or 
system/segment/element/subsystem/etc. qualification testing; 

c) The status of the system/segment/element/subsystem/etc. to be tested. 

E.3.8 Test results reviews 

These reviews are held to resolve open issues regarding the results of software item qualification 
testing or system/segment/element/subsystem/etc. qualification testing. 

E.3.9 Software usability reviews 

These reviews are held to resolve open issues regarding one or more of the following: 

a) The readiness of the software for installation at user sites; 

b) The user and operator manuals; 

c) The software version descriptions; 

d) The status of installation preparations and activities. 

E.3.10 Software maintenance reviews 

These reviews are held to resolve open issues regarding one or more of the following: 

a) The readiness of the software for transition to the maintenance organization; 

b) The software product specifications; 

c) The software maintenance manuals; 

d) The software version descriptions; 

e) The status of transition preparations and activities, including transition of the software 
development environment, if applicable. 

E.3.11 Critical requirements reviews 

These reviews are held to resolve open issues regarding the handling of critical requirements, such as 
those for safety, security, and privacy. (See Section 4.2.5.) 


E-2 



Appendix F. Candidate management indicators 


F.1 Scope 

This appendix identifies a set of management indicators that might be used on a software 
development project. This appendix is not a mandatory part of this standard. The information 
provided is intended for guidance only. 

F.2 Candidate indicators 

Given below is a set of candidate management indicators that might be used on a software 
development project. There is no intent to impose these indicators or to preclude others. 

a) Requirements volatility: total number of requirements and requirement changes over time. 

b) Software size: planned and actual number of units, lines of code, or other size measurement 
over time. 

c) Software staffing: planned and actual staffing levels over time. 

d) Software complexity: complexity of each software unit. 

e) Software progress: planned and actual number of software units designed, implemented, unit 
tested, and integrated over time. 

f) Problem/change report status: total number, number closed, number opened in the current 
reporting period, age, severity. 

g) Build release content: planned and actual number of software units released in each build. 

h) Build release volatility 13 : planned and actual number of software requirements implemented 
in each build. 

i) Computer hardware resource utilization: planned and actual use of computer hardware 
resources (such as processor capacity, memory capacity, input/output device capacity, 
auxiliary storage device capacity, and communications/network equipment capacity) over 
time. 

j) Milestone performance: planned and actual dates of key project milestones. 

k) Scrap/rework: amount of resources expended to replace or revise software products after 
they are placed under any level of configuration control above the individual 
author/developer level. 

l) Effect of reuse: a breakout of each of the indicators above for reused versus new software 
products. 

m) Cost performance 13 : identifies how efficiently the project team has turned costs into progress 
to date. 

n) Budgeted cost of work performed 13 : identifies the cumulative work that has been delivered 
to date. 


13 This is from Metrics-based Software Acquisition Management, Aerospace Report No. TOR-2004(3909)-3405 [1], 


F-l 



Additional information can be found in the Practical Software Measurement: Objective Information 
for Decision Makers, Addison-Wesley, 2001 [10]; Practical Software and System Measurement, 
Version 4.0c, March 2003 [5]; and Metrics-based Software Acquisition Management, Aerospace 
Report No. TOR-2004(3909)-3405 [1]. 


F-2 



Appendix G. Guidance on contracting for delivery of software products 


G.1 Scope 

This appendix provides guidance to the acquirer on the deliverables to be required on a software 
development project. This appendix is not a mandatory part of this standard. The information 
provided is intended for guidance only. 

G.2 Contracting for deliverables 

This standard has been worded to differentiate between the planning/engineering activities that make 
up a software development project and the generation of deliverables. A key objective of this 
wording is to eliminate the notion that the acquirer must contractually require a given deliverable in 
order to have planning or engineering work take place. Under this standard, the planning and 
engineering work takes place regardless of which deliverables are contractually required, unless a 
given activity is tailored out of the standard. In addition, joint technical reviews have been included 
to review the results of that work in its natural form, without the generation of deliverables. 
Deliverables are to be contractually required only when there is a genuine need to have planning or 
engineering information transformed into a deliverable, recognizing that this transformation requires 
time and effort that would otherwise be spent on the engineering effort. Block 3 of each DID 
provides information that is helpful in deciding whether the corresponding deliverable shall be 
contractually required. 

G.3 Scheduling deliverables 

This standard has been structured to support a variety of development strategies and to provide the 
developer with flexibility in laying out a software development process that will best suit the work to 
be done. All of this flexibility can be canceled by rigid scheduling of deliverables in the contract. If 
the contract lays out a strict “waterfall” sequence of deliverables, little room is left to propose 
innovative development processes. If the contract forces all software items into lock-step with each 
other, little room is left to develop the software items in an optimum order. To the maximum extent 
possible, the contract is to avoid such pre-determination, leaving the door open for incremental 
delivery of software products, staggered development of software items, and other variations to 
optimize the software development effort. The developer’s SDP will lay out a proposed schedule that 
meets the constraints in the contract. Final agreement on scheduling can take place at that time. 

G.4 Format of deliverables 

Traditional deliverables (such as DIDs) take the form of paper documents exactly following required 
formats and structure. While this form works well for some deliverables, it is not the only form, and 
alternatives should be considered. One variation from paper documents is word processing files 
containing those documents. This format saves paper, but still requires the developer to format and 
structure the information as required. Another variation is specifying that a paper or word processor 
document is to include all required contents but may be in the developer’s format. Yet another 
variation is allowing deliverables to take forms that are not traditional documents at all, such as data 
in computer-aided software engineering (CASE) tools. These variations in required format can be 
specified in the contract, minimizing the time spent transforming actual work products into 
deliverables. 


G-l 



G.5 Tailoring the content requirements for deliverables 

Tailoring the content requirements for deliverables consists of deleting requirements for unneeded 
information and making other changes that do not increase the required workload, such as combining 
two documents under one cover. DID tailoring for deliverables is specified in the contract. 


G-2 



Appendix H. Software Development Plan Template 


This appendix is a mandatory part of the standard. The numbering shown below in sections 4 and 5 is 
consistent with the paragraphs in this standard. 

Referenced information cited in Paragraphs 4, 5, 6, and 7 shall be provided as attachments to the plan. 

1. Scope. This section shall be divided into the following paragraphs. 

1.1 Identification . This paragraph shall contain a full identification of the system and the software 
to which this document applies, including, as applicable, identification number(s), title(s), 
abbreviation(s), version number(s), and release number(s). 

1.2 System overview . This paragraph shall briefly state the purpose of the system and the software 
to which this document applies. It shall describe the general nature of the system and software; 
summarize the history of system development, operation, and maintenance; identify the project 
sponsor, acquirer, user, developer, and support agencies; identify current and planned operating sites; 
and list other relevant documents. 

1.3 Document overview . This paragraph shall summarize the purpose and contents of this 
document and shall describe any security or privacy considerations associated with its use. 

1.4 Relationship to other plans . This paragraph shall describe the relationship, if any, of the SDP 
to other project management plans. 

2. Referenced documents . This section shall list the number, title, revision, and date of all 
documents referenced in this plan. This section shall also identify the source for all documents 
not available through normal Government stocking activities. 

3. Overview of required work . This section shall be divided into paragraphs as needed to establish 
the context for the planning described in later sections. It shall include, as applicable, an 
overview of: 

a. Requirements and constraints on the system and software to be developed 

b. Requirements and constraints on project documentation 

c. Position of the project in the system life cycle 

d. The selected program/acquisition strategy or any requirements or constraints on it 

e. Requirements and constraints on project schedules and resources 

f. Other requirements and constraints, such as on project security, privacy, methods, 

standards, interdependencies in hardware and software development, etc. 

4. General requirements . This section shall be divided into the following paragraphs. Provisions 
corresponding to non-required activities may be satisfied by the words "Not applicable." If 
different builds or different software on the project require different planning, these differences 
shall be noted in the paragraphs. In addition to the content specified below, each paragraph shall 
identify applicable risks/uncertainties and plans for dealing with them. 


H-l 



4.1 Software development process . This paragraph shall describe the software development 
process to be used. The planning shall cover all contractual clauses concerning this topic and 
identification of the software developmental life cycle model(s) to be used, including: planned 
builds, if applicable, their build objectives, and the software development activities to be performed in 
each build. 

4.2 General requirements for software development . This paragraph shall be divided into the 
following subparagraphs. 

4.2.1 Software development methods . This paragraph shall describe or reference the software 
development methods to be used. Included shall be descriptions of the manual and automated tools 
and procedures to be used in support of these methods. The methods shall cover all contractual 
clauses concerning this topic. Reference may be made to other paragraphs in this plan if the methods 
are better described in context with the activities to which they will be applied. 

4.2.2 Standards for software products . This paragraph shall describe or reference the standards to 
be followed for representing requirements, design, code, test cases, test procedures, and test results. 
The standards shall cover all contractual clauses concerning this topic. Reference may be made to 
other paragraphs in this plan if the standards are better described in context with the activities to 
which they will be applied. Standards for code shall be provided for each programming language to 
be used. They shall include at a minimum: 

a. Standards for format (such as indentation, spacing, capitalization, and order of 
information) 

b. Standards for header comments (requiring, for example, name/identifier of the code; 
version identification; modification history; purpose; requirements and design decisions 
implemented; notes on the processing (such as algorithms used, assumptions, constraints, 
limitations, and side effects); and notes on the data (inputs, outputs, variables, data 
structures, etc.) 

c. Standards for other comments (such as required number and content expectations) 

d. Naming conventions for variables, parameters, packages, procedures, files, etc. 

e. Restrictions, if any, on the use of programming language constructs or features 

f. Restrictions, if any, on the complexity of code aggregates 

4.2.3 Traceability . This paragraph shall describe the approach to be followed for establishing and 
maintaining bi-directional traceability between levels of requirements, between requirements and 
design, between design and the software that implements it, between requirements and qualification 
test information, and between computer hardware resource utilization requirements and measured 
computer hardware resource utilization. 

4.2.4 Reusable software products . This paragraph shall be divided into the following 
subparagraphs. 

4.2.4.1 Incorporating reusable software products . This paragraph shall describe the approach 
to be followed for identifying, evaluating, and incoiporating reusable software products, 
including the scope of the search for such products and the criteria to be used for their 
evaluation. It shall cover all contractual clauses concerning this topic. Candidate or selected 
reusable software products known at the time this plan is prepared or updated shall be 


H-2 



identified and described, together with benefits, drawbacks, and restrictions, as applicable, 
associated with their use. 

4.2.4.2 Developing reusable software products . This paragraph shall describe the approach 
to be followed for identifying, evaluating, and reporting opportunities for developing reusable 
software products. It shall cover all contractual clauses concerning this topic. 

4.2.5 Assurance of critical requirements . This paragraph shall be divided into the following 
subparagraphs to describe the approach to be followed for handling requirements designated critical. 
The planning in each subparagraph shall cover all contractual clauses concerning the identified topic. 

4.2.5.1 Safety 

4.2.5.2 Security 

4.2.5.3 Privacy protection 

4.2.5.4 Dependability, reliability, maintainability, and availability 

4.2.5.5 Assurance of other mission-critical requirements as agreed to by the acquirer and 
developer 

4.2.6 Computer hardware resource utilization . This paragraph shall describe the approach to be 
followed for allocating computer hardware resources and monitoring their utilization. It shall cover 
all contractual clauses concerning this topic. 

4.2.7 Recording rationale . This paragraph shall describe the approach to be followed for recording 
rationale that will be useful to the support agency for key decisions made on the project. It shall 
interpret the term "key decisions" for the project and state where the rationale are to be recorded. It 
shall cover all contractual clauses concerning this topic. 

4.2.8 Access for acquirer review . This paragraph shall describe the approach to be followed for 
providing the acquirer or its authorized representative access to developer and subcontractor facilities 
for review of software products and activities. It shall cover all contractual clauses concerning this 
topic. 

5. Plans for performing detailed software development activities . This section shall be divided into 
the following paragraphs. Provisions corresponding to non-required activities may be satisfied by the 
words "Not applicable." If different builds or different software on the project require different 
planning, these differences shall be noted in the paragraphs. The discussion of each activity shall 
include the approach (plans, processes, methods, procedures, tools, roles and responsibilities) to be 
applied to: 1) the analysis or other technical tasks involved, 2) the recording of results, and 3) the 
preparation of associated deliverables, if applicable. For each activity, include entrance criteria, 
inputs, tasks to be accomplished and products to be produced, verifications to be used (to ensure tasks 
are performed according to their defined processes and products meet their requirements), outputs, 
and exit criteria. The discussion shall also identify applicable risks/uncertainties and plans for dealing 
with them. Reference may be made to 4.2.1 if applicable methods are described there. 

5.1 Project planning and oversight . This paragraph shall be divided into the following 
subparagraphs to describe the approach to be followed for project planning and oversight. The 
planning in each subparagraph shall cover all contractual clauses regarding the identified topic. 

5.1.1 Software development planning 

5.1.2 Software item test planning 


H-3 



5.1.3 System test planning 

5.1.4 Planning for software transition to operations 

5.1.5 Planning for software transition to maintenance 

5.1.6 Following and updating plans 

5.2 Establishing a software development environment . This paragraph shall be divided into the 
following subparagraphs to describe the approach to be followed for establishing, controlling, and 
maintaining a software development environment. The planning in each subparagraph shall cover all 
contractual clauses regarding the identified topic. 

5.2.1 Software engineering environment 

5.2.2 Software integration and test environment 

5.2.3 Software development library 

5.2.4 Software development files 

5.2.5 Non-deliverable software 

5.3 System requirements analysis . This paragraph shall be divided into the following 
subparagraphs to describe the approach to be followed for participating in system requirements 
analysis. The planning in each subparagraph shall cover all contractual clauses regarding the 
identified topic. 

5.3.1 Analysis of user input 

5.3.2 Operational concept 

5.3.3 System requirements 

5.4 System design . This paragraph shall be divided into the following subparagraphs to describe 
the approach to be followed for participating in system design. The planning in each subparagraph 
shall cover all contractual clauses regarding the identified topic. 

5.4.1 System-wide design decisions 

5.4.2 System architectural design 

5.5 Software requirements analysis . This paragraph shall describe the approach to be followed for 
software requirements analysis. The approach shall cover all contractual clauses concerning this 
topic. 

5.6 Software design . This paragraph shall be divided into the following subparagraphs to describe 
the approach to be followed for software design. The planning in each subparagraph shall cover all 
contractual clauses regarding the identified topic. 

5.6.1 Software item-wide design decisions 

5.6.2 Software item architectural design 

5.6.3 Software item detailed design 

5.7 Software implementation and unit testing . This paragraph shall be divided into the following 
subparagraphs to describe the approach to be followed for software implementation and unit testing. 
The planning in each subparagraph shall cover all contractual clauses regarding the identified topic. 

5.7.1 Software implementation 

5.7.2 Preparing for unit testing 

5.7.3 Performing unit testing 

5.7.4 Revision and retesting 

5.7.5 Analyzing and recording unit test results 


H-4 



5.8 Unit integration and testing . This paragraph shall be divided into the following subparagraphs 
to describe the approach to be followed for unit integration and testing. The planning in each 
subparagraph shall cover all contractual clauses regarding the identified topic. 

5.8.1 Preparing for unit integration and testing 

5.8.2 Performing unit integration and testing 

5.8.3 Revision and retesting 

5.8.4 Analyzing and recording unit integration and test results 

5.9 Software item qualification testing . This paragraph shall be divided into the following sub- 
paragraphs to describe the approach to be followed for software item qualification testing. The 
planning in each subparagraph shall cover all contractual clauses regarding the identified topic. 

5.9.1 Independence in software item qualification testing 

5.9.2 Testing on the target computer system 

5.9.3 Preparing for software item qualification testing 

5.9.4 Dry run of software item qualification testing 

5.9.5 Performing software item qualification testing 

5.9.6 Revision and retesting 

5.9.7 Analyzing and recording software item qualification test results 

5.10 Software/hardware item integration and testing . This paragraph shall be divided into the 
following subparagraphs to describe the approach to be followed for participating in 
software/hardware item integration and testing. The planning in each subparagraph shall cover all 
contractual clauses regarding the identified topic. 

5.10.1 Preparing for software/hardware item integration and testing 

5.10.2 Performing software/hardware item integration and testing 

5.10.3 Revision and retesting 

5.10.4 Analyzing and recording software/hardware item integration and test results 

5.11 System qualification testing . This paragraph shall be divided into the following subparagraphs 
to describe the approach to be followed for participating in system qualification testing. The planning 
in each subparagraph shall cover all contractual clauses regarding the identified topic. 

5.11.1 Independence in system qualification testing 

5.11.2 Testing on the target computer system 

5.11.3 Preparing for system qualification testing 

5.11.4 Dry run of system qualification testing 

5.11.5 Performing system qualification testing 

5.11.6 Revision and retesting 

5.11.7 Analyzing and recording system qualification test results 

5.12 Preparing for software transition to operations . This paragraph shall be divided into the 
following subparagraphs to describe the approach to be followed for preparing for software use. The 
planning in each subparagraph shall cover all contractual clauses regarding the identified topic. 

5.12.1 Preparing the executable software 

5.12.2 Preparing version descriptions for user sites 

5.12.3 Preparing user manuals 

5.12.3.1 Software user manuals 

5.12.3.2 Computer operations manuals 


H-5 



5.12.4 Installation at user sites 


5.13 Preparing for software transition to maintenance . This paragraph shall be divided into the 
following subparagraphs to describe the approach to be followed for preparing for software transition 
to maintenance. The planning in each subparagraph shall cover all contractual clauses regarding the 
identified topic. 

5.13.1 Preparing the executable software 

5.13.2 Preparing source files 

5.13.3 Preparing version descriptions for the maintenance site 

5.13.4 Preparing the "as built" software item design and other related information 

5.13.5 Updating the system/subsystem design description 

5.13.6 Updating the software requirements 

5.13.7 Updating the system requirements 

5.13.8 Preparing maintenance manuals 

5.13.8.1 Computer programming manuals 

5.13.8.2 Firmware support manuals 

5.13.9 Transition to the designated maintenance site 

5.14 Software configuration management . This paragraph shall be divided into the following 
subparagraphs to describe the approach to be followed for software configuration management. The 
planning in each subparagraph shall cover all contractual clauses regarding the identified topic. 

5.14.1 Configuration identification 

5.14.2 Configuration control 

5.14.3 Configuration status accounting 

5.14.4 Configuration audits 

5.14.5 Packaging, storage, handling, and delivery 

5.15 Software peer reviews and product evaluations . This paragraph shall be divided into the 
following subparagraphs to describe the approach to be followed for software peer reviews and 
product evaluations. The planning in each subparagraph shall cover all contractual clauses regarding 
the identified topic. 

5.15.1 Software peer reviews 

5.15.1.1 Prepare for software peer reviews 

5.15.1.2 Conduct peer reviews 

5.15.1.3 Analyze peer review data 

5.15.2 Software product evaluations 

5.15.2.1 In-process and final software product evaluations 

5.15.2.2 Software product evaluation records 

5.15.2.3 Independence in software product evaluations 

5.16 Software quality assurance . This paragraph shall be divided into the following subparagraphs 
to describe the approach to be followed for software quality assurance. The planning in each 
subparagraph shall cover all contractual clauses regarding the identified topic. 

5.16.1 Software quality assurance evaluations 

5.16.2 Software quality assurance records 

5.16.3 Independence in software quality assurance 

5.16.4 Software quality assurance noncompliance issues 


H-6 



5.17 Corrective action . This paragraph shall be divided into the following subparagraphs to 
describe the approach to be followed for corrective action. The planning in each subparagraph shall 
cover all contractual clauses regarding the identified topic. 

5.17.1 Problem/change reports 

These reports shall include items to be recorded such as: project name, originator, 
problem number, problem name, software element or document affected, origination 
date, category and severity, description, analyst assigned to the problem, date 
assigned, date completed, analysis time, recommended solution, impacts, problem 
status, approval of solution, follow-up actions, corrector, correction date, problem 
type (e.g., using Orthogonal Defect Classification), version where corrected, 
correction time, and description of solution implemented. 

5.17.2 Corrective action system 

5.18 Joint technical and management reviews . This paragraph shall be divided into the following 
subparagraphs to describe the approach to be followed for joint technical and management reviews. 
The planning in each subparagraph shall cover all contractual clauses regarding the identified topic. 

5.18.1 Joint technical reviews 

5.18.2 Joint management reviews 

5.19 Risk management . This paragraph shall describe the approach for performing risk 
management. The planning shall cover all contractual clauses regarding the identified topic. 

5.20 Software management indicators . This paragraph shall describe the approach to be used for 
software measurement throughout the life cycle. This paragraph shall also include the specific 
software measurements to be used (that is, collected, analyzed, reported, and used for decision 
making, corrective actions and reporting to the customer), including which measurements will be 
reported by lifecycle activity (e.g., requirements, design, code, integration, test). For each 
measurement the elements of the measurement construct as defined Figure A-l of Practical Software 
Measurement: Objective Information for Decision Makers [10] shall be completed. The bla nk 
Elements of Measurement Construct form is available at the Practical Software and Systems 
Measurement web site. 

5.21 Security and privacy . This paragraph shall describe the approach for meeting the security and 
privacy requirements. The planning shall cover all contractual clauses regarding the identified topic. 

5.22 Subcontractor management . This paragraph shall describe the approach for performing 
subcontractor management. The planning shall cover all contractual clauses regarding the identified 
topic. 

5.23 Interface with software independent verification and validation (IV&V) agents . This 
paragraph shall describe the approach for interfacing with the software IV&V agents. The planning 
shall cover all contractual clauses regarding the identified topic. 

5.24 Coordination with associate developers . This paragraph shall describe the approach for 
performing the coordination with associate developers, working groups, and interface groups. The 
planning shall cover all contractual clauses regarding the identified topic. 


H-7 



5.25 Improvement of project processes . This paragraph shall describe the approach for performing 
the improvement of project processes. The planning shall cover all contractual clauses regarding the 
identified topic. 

6. Schedules and activity network . This section shall present: 

a. Schedule(s) identifying the activities in each build and showing initiation of each activity, 
availability of draft and final deliverables and other milestones, and completion of each 
activity 

b. An activity network, depicting sequential relationships and dependencies among 
activities and identifying those activities that impose the greatest time restrictions on the 
project 

7. Project organization and resources . This section shall be divided into the following paragraphs to 
describe the project organization and resources to be applied in each build. 

7.1 Project organization . This paragraph shall describe the organizational structure to be used on 
the project, including the organizations involved, their relationships to one another, and the authority 
and responsibility of each organization for carrying out required activities. 


7.2 Project resources . This paragraph shall describe the resources to be applied to the project. It 
shall include, as applicable: 

a. Personnel resources, including: 

1) The estimated staff-loading for the project (number of personnel over time) 

2) The breakdown of the staff-loading numbers by responsibility (for example, 
management, software engineering, software testing, software configuration 
management, software product evaluation, software quality assurance) 

3) A breakdown of the skill levels, geographic locations, and security clearances of 
personnel performing each responsibility 

4) The rationale for effort, staff loading and schedule estimates, including software cost 
and schedule estimation techniques, the input to those techniques (e.g., software size and 
software cost driver parameters), and any assumptions made 

b. Overview of developer facilities to be used, including geographic locations in which the 
work will be performed, facilities to be used, and secure areas and other features of the 
facilities as applicable to the contracted effort. 

c. Acquirer-furnished equipment, software, services, documentation, data, and facilities 
required for the contracted effort. A schedule detailing when these items will be needed 
shall also be included. 

d. Other required resources, including a plan for obtaining the resources, dates needed, and 
availability of each resource item. 


8. Notes . This section shall contain any general information that aids in understanding this 
document (e.g., background information, glossary, rationale). This section shall include an 
alphabetical listing of all acronyms, abbreviations, and their meanings as used in this document 
and a list of any terms and definitions needed to understand this document. 


H-8 



A. Appendixes . Appendixes may be used to provide information published separately for 
convenience in document maintenance (e.g., charts, classified data). As applicable, each appendix 
shall be referenced in the main body of the document where the data would normally have been 
provided. Appendixes may be bound as separate documents for ease in handling. Appendixes shall 
be lettered alphabetically (A, B, etc.). 


H-9 




SMC Standard Improvement Proposal 

INSTRUCTIONS 

1. Complete blocks 1 through 7. All blocks must be completed. 

2. Send to the Preparing Activity specified in block 8. 

NOTE: Do not be used to request copies of documents, or to request waivers, or clarification of requirements on 
current contracts. Comments submitted on this form do not constitute or imply authorization to waive any portion of 
the referenced document(s) or to amend contractual requirements. Comments submitted on this form do not 
constitute a commitment by the Preparing Activity to implement the suggestion; the Preparing Authority will 
coordinate a review of the comment and provide disposition to the comment submitter specified in Block 6. 


SMC STANDARD 

CHANGE 

RECOMMENDATION: 

1. Document Number 

2. Document Date 

3. Document Title 



4. Nature of Change 

(Identify paragraph number; include proposed revision language and supporting data. Attach extra sheets as needed.) 


5. Reason for Recommendation 


6. Submitter Information __ 

a. Name b. Organization 


c. Address d. Telephone 


e. E-mail address 7. Date Submitted 


8. Preparing Activity Space and Missile Systems Center 

AIR FORCE SPACE COMMAND 
483 N. Aviation Blvd. 

El Segundo, CA 91245 
Attention: SMC/EAE 


March 2008